Commissioning checklist 3
0020251822_01 System installation instructions
3
Work
Comments/settings
7
Use cold pipe clips to install the brine pipes in the house
Prevent thermal bridges
8
Use the correct brine fluid
Monoethylene glycol, essential for fault-free operation.
9
Use the correct mixing ratio of monoethylene glycol to water
3:7, efficient operation only when the defined mixing ratio
is used
10
Use a refractometer to check the mixing ratio
Efficient operation only when the defined mixing ratio is
used
11
Choke the output of the filling pump
Reduce the penetration of air in the brine circuit.
12
Sufficiently dimension the VWZ MEH 61's expansion vessel for the
heating circuit
No expansion vessel present in the heat pump.
13
Connect the heat pump via a separately fused plug socket
Observe the connection conditions in accordance with
the data plate.
14
Connect the back-up heater from the VWZ MEH 61 via a 400 V con-
nection
Observe the connection conditions in accordance with
the data plate.
15
Use connection terminals when connecting multiple conductors
Prevent communication faults.
16
Check all cable connections for tensile strength
17
Visually check all cable connections for damage
3
Commissioning checklist
3.1
VWZ MEH 61
Work
Comments/settings
1
Start the installation assistant
If it is not started automatically
2
Language
Select
3
Check program: Purging of building circuit active
Starts automatically, end after approx. 30 minutes
4
Contact details
Enter on the VRC 700
5
End the installation assistant?
Yes
6
Menu
→
Installer level
→
Test menu
→
Sensor/actuator test
7
Check T.1.63
SP1 temperature
Actual cylinder temperature
3.2
VWS 36/4.1 230V
Work
Comments/settings
8
Start the installation assistant
OK
9
Language
Select
10
Freeze protection
−
10 °C
11
Purge environment and building circuit
No
12
Purge building circuit
No
13
Check program: Purge environment circuit
Yes
, test active, end after approx. 30 minutes
14
Contact details
Enter on the VRC 700
15
End the installation assistant?
Yes
16
Menu
→
Installer level
→
Test menu
→
Sensor/actuator test
17
T.82
Building circuit pressure
Check, at least 1500-2000 mbar
18
T.101
Environment circuit pressure
Check, at least 1500-2000 mbar
19
T.146
Outside temperature
Check, actual temperature display