Startup Procedure
10.
Now start another immediate regeneration and allow the system to backwash and rinse for the full cy-
cles. The water coming out of the drain should be running clear. If not, repeat this step until the water
is clear.
11.
Once the valve is back to the “Service” position, open a bath tub faucet or another large usage valve.
12.
Record the inlet and outlet pressures on the installed inlet and outlet gauges. The difference in these
values will be the “Service Pressure Drop”.
13.
Record the pressure values of the inlet and outlet gauges daily. Once an addition pressure drop of 6-
10 PSI is observed, the filter must be backwashed. The number of days recorded will be the back-
wash frequency.
14.
Now go back to the “Regen. Days” setting in the “Main Menu” and input the number of days between
the original startup and when the additional pressure drop was observed. If the system does not show
a pressure drop after 14 days, set the “Regen Days” to 14 days. This will ensure the bed is being lifted
and redistributed to prevent channeling through the media.
15.
Once the final “Regen Days” frequency has been programmed, the system will backwash automatical-
ly going forward.
The installation is now complete!
Installation, Operation and Maintenance Manual
Models: 089-IF-150, 089-IF-250, 089-IF-400,
089-IF-500
Rinsing...
Any Key 3S To Next
4:48
76%
Backwashing...
Any Key 3S To Next
14:48
1%
Date & Time:
20-Dec-2015 12:12AM
Days To Regen:01