Maintenance Information
Meter Calibration
The 2-LA-2 meters may occasionally need to be calibrated. This is accomplished by adjusting the
GR Zero Set potentiometer, located to the left of each channel’s Meter switch.
The procedure for adjusting the meter is as follows:
1.
Power on the 2-LA-2 and allow it to warm up for five minutes.
2.
Set the Meter switch for the channel being calibrated to its up (GR) position.
3.
Set the Peak Reduction control fully off (turn the knob fully counterclockwise) and make sure
there is no signal present.
4.
Use a small screwdriver to slowly adjust the GR Zero Set potentiometer so that the meter
reads 0 dB. Watch how the meter settles before completing the calibration.
Changing the Internal Voltage Selector
The 2-LA-2 can operate at 100V (for use in Japan), 120V, or 240V. To change the internal voltage
selector, wait 5 minutes after power down, then
unplug the AC power cord from the rear chassis
.
Remove the top cover. As shown in the photograph below, there is a connector that can be plugged
into one location or another to configure the unit for different voltage operation. This connector is part
of the wiring that comes from the power transformer located at the rear center of the 2-LA-2.
(NOTE: This photograph shows the unit configured for 120V operation.)