INSPECTION

As soon as a unit is received, it should be inspected for possible dam-
age during transit. If damage is evident, the extent of the damage
should be noted on the carrier’s freight bill. A separate request for
inspection by the carrier’s agent should be made in writing. Also, before
installation the unit should be checked for screws or bolts, which may
have loosened in transit. There are no shipping or spacer brackets
which need to be removed.

FURNACE LOCATION AND CLEARANCES

The furnace shall be located using the following guidelines:

1.

Where a minimum amount of air intake/vent piping and elbows will
be required.

2.

As centralized with the air distribution as possible.

3.

Where adequate combustion air will be available (particularly
when the appliance is not using outdoor combustion air).

4.

Where it will not interfere with proper air circulation in the confined
space.

5.

Where the outdoor vent terminal will not be blocked or restricted.
Refer to “VENT CLEARANCES” located in SECTION VI of these
instructions. These minimum clearances must be maintained in
the installation.

6.

Where the unit will be installed in a level position with no more
than 1/4” (6.4 mm) slope side-to-side and front-to-back.

Installation in freezing temperatures:

1.

Furnace shall be installed in an area where ventilation facilities
provide for safe limits of ambient temperature under normal oper-
ating conditions. Ambient temperatures may fall below 32° F (0° C)
providing the flue temperature does not fall below 260° F (127° C)
at any point in the flue pipe between the furnace and the chimney
or a B-Vent. The flue products will condense in the vent pipe if the
flue temperature falls below 260° F (127° C) causing the vent pipe
to deteriorate rapidly.

2.

Do not allow return air temperature to be below 55º F (13° C) for
extended periods. To do so may cause condensation to occur in
the main heat exchanger, leading to premature heat exchanger
failure. 

3.

If this furnace is installed in an unconditioned space and an
extended power failure occurs, there will be potential damage to
the internal components. Following a power failure situation, do
not operate the unit until inspection and repairs are performed.

Clearances for access:

Ample clearances should be provided to permit easy access to the unit.
The following minimum clearances are recommended:

1.

Twenty-four (24) inches (61 cm) between the front of the furnace
and an adjacent wall or another appliance, when access is
required for servicing and cleaning.

2.

Eighteen (18) inches (46 cm) at the side where access is required
for passage to the front when servicing or for inspection or
replacement of flue/vent connections.

In all cases, accessibility clearances shall take precedence over clear-
ances for combustible materials where accessibility clearances are
greater.

Installation in a residential garage:

A gas-fired furnace for installation in a residential garage must be
installed so the burner(s) and the ignition source are located not less
than 18 inches (46 cm) above the floor, and the furnace must be located
or protected to avoid physical damage by vehicles.

The furnace area must not be used as a broom closet or for any
other storage purposes, as a fire hazard may be created. Never
store items such as the following on, near, or in contact with the fur-
nace.

1. Spray or aerosol cans, rags, brooms, dust mops, vacuum

cleaners or other cleaning tools.

2. Soap powders, bleaches, waxes, or other cleaning com-

pounds; plastic items or containers; gasoline, kerosene, ciga-
rette lighter fluid, dry cleaning fluids or other volatile fluid.

3. Paint thinners and other painting compounds.
4. Paper bags, boxes, or other paper products

Never operate the furnace with the blower door removed. To
do so could result in serious personal injury and/or equipment
damage.

FOR FURNACES INSTALLED IN THE COMMON-

WEALTH  OF MASSACHUSETTS ONLY

For all side wall horizontally vented gas fueled equipment installed in
every dwelling, building or structure used in whole or in part for resi-
dential purposes, including those owned or operated by the Com-
monwealth and where the side wall exhaust vent termination is less
than seven (7) feet above finished grade in the area of the venting,
including but not limited to decks and porches, the following require-
ments shall be satisfied:

1.

INSTALLATION OF CARBON MONOXIDE DETECTORS. 

At

the time of installation of the side wall horizontal vented gas
fueled equipment, the installing plumber or gasfitter shall
observe that a hard wired carbon monoxide detector with an
alarm and battery back-up is installed on the floor level where
the gas equipment is to be installed. In addition, the installing
plumber or gasfitter shall observe that a battery operated or
hard wired carbon monoxide detector with an alarm is installed
on each additional level of the dwelling, building or structure
served by the side wall horizontal vented gas fueled equipment.
It shall be the responsibility of the property owner to secure the
services of qualified licensed professionals for the installation of
hard wired carbon monoxide detectors

a.

In the event that the side wall horizontally vented gas
fueled equipment is installed in a crawl space or an attic,
the hard wired carbon monoxide detector with alarm and
battery back-up may be installed on the next adjacent floor
level.

b.

In the event that the requirements of this subdivision can
not be met at the time of completion of installation, the
owner shall have a period of thirty (30) days to comply with
the above requirements; provided, however, that during
said thirty (30) day period, a battery operated carbon mon-
oxide detector with an alarm shall be installed.

2.

APPROVED CARBON MONOXIDE DETECTORS. 

Each car-

bon monoxide detector as required in accordance with the
above provisions shall comply with NFPA 720 and be ANSI/UL
2034 listed and IAS certified.

3.

SIGNAGE. 

A metal or plastic identification plate shall be perma-

nently mounted to the exterior of the building at a minimum
height of eight (8) feet above grade directly in line with the
exhaust vent terminal for the horizontally vented gas fueled
heating appliance or equipment. The sign shall read, in print
size no less than one-half (1/2) inch in size, "

GAS VENT

DIRECTLY BELOW. KEEP CLEAR OF ALL OBSTRUC-
TIONS

".

4.

INSPECTION. 

The state or local gas inspector of the side wall

horizontally vented gas fueled equipment shall not approve the
installation unless, upon inspection, the inspector observes car-
bon monoxide detectors and signage installed in accordance
with the provisions of 248 CMR 5.08(2)(a)1 through 4.

Improper installation in an ambient below 32ºF (0.0° C) could create
a hazard, resulting in damage, injury or death.

Содержание AHT8-UH

Страница 1: ...RING DIAGRAM 30 LIST OF FIGURES Dimensions 6 Typical Attic Installation 7 Typical Suspended Furnace Crawl Space Installation 7 Side Return Cutout Markings 8 Gas Valve 8 Upflow Gas Piping 8 Horizontal...

Страница 2: ...s from combustible materials as listed under Clearances to Combustibles in Table 1 Provide clearances for servicing ensuring that service access is allowed for both the burners and blower These models...

Страница 3: ...d Never store items such as the following on near or in contact with the fur nace 1 Spray or aerosol cans rags brooms dust mops vacuum cleaners or other cleaning tools 2 Soap powders bleaches waxes or...

Страница 4: ...t the specified external static pressure and within the air temperature rise specified on the nameplate Table 2 is a guide for determining whether the rectangular duct system that the furnace is being...

Страница 5: ...plenum On all installations without a coil a removable access panel is recommended in the outlet duct such that smoke or reflected light would be observable inside the casing to indi cate the presenc...

Страница 6: ...essibility IMPORTANT If an external mounted filter rack is being used see the instructions provided with that accessory for proper hole cut size HORIZONTAL MODELS IMPORTANT This furnace may be install...

Страница 7: ...removed and a new plenum installed that is the proper size for the new furnace Attach the return plenum to the furnace inlet duct flanges This is typi cally through the use of S cleat material when a...

Страница 8: ...fer to Table 15 SECTION IV GAS PIPING GAS SAFETY IMPORTANT Plan your gas supply before determining the correct gas pipe entry Use 90 degree service elbow s or short nipples and con ventional 90 degree...

Страница 9: ...e gas valve body is a very thin casting that cannot take any external pressure Never apply a pipe wrench to the body of the gas valve when installing piping A wrench must be placed on the octag onal h...

Страница 10: ...o the proper gas orifice size when the furnace is installed Do not attempt to drill out any orifices to obtain the proper orifice size Drilling out a gas orifice will cause misalignment of the burner...

Страница 11: ...ty is corrected Refer to FURNACE DIAGNOSTICS section of the User s Information Maintenance Service Manual provided with this furnace for symptoms of reversed power supply polarity LOW VOLTAGE CONTROL...

Страница 12: ...lt Common is optional when used with batteries Thermostat Installer Setup Number 1 System Type must be set to 6 2 Heat 2 Cool Conventional R 24 Volt Hot Heat XFMR W2 Second Stage Heat RC 24 Volt Hot C...

Страница 13: ...BSG Bonnet Sensor Bonnet Sensor Optional BS Bonnet Sensor W2 Second Stage Auxiliary Heat W2 Second Stage Auxiliary Heat AUX Auxiliary Heat E W1 First Stage Auxiliary Heat E W1 First Stage Auxiliary H...

Страница 14: ...gas supplies must be provided as specified with these instruc tions Since the furnaces are side by side with no space between gas supplies must enter on the right and left respectively All gas piping...

Страница 15: ...wers will come on in the selected continuous fan speed and will stay on until the G signal is removed SECTION VI VENT SYSTEM VENT SAFETY This Category I furnace is designed for residential application...

Страница 16: ...ese instructions Approved Modular Homes must be vented with an approved roof jack and may not be common vented with other appliances VENTING Category I venting consists of vertically venting one or mo...

Страница 17: ...se masonry chimney kits 3 The chimney must extend at least three 3 ft 0 91 cm above the highest point where it passes through a roof of a building and at least two 2 feet higher than any portion of th...

Страница 18: ...tion should be located where it will not be affected by wind gusts light snow airborne leaves or allow recirculation of flue gases 4 Termination should be located where it will not be damaged or expos...

Страница 19: ...anufacturer s instructions Dampers Louvers and Grilles Canada Only 1 The free area of a supply air opening shall be calculated by sub tracting the blockage area of all fixed louvers grilles or screens...

Страница 20: ...horizontally from the burner level of the appliance Refer to COMBUSTION AIR SOURCE FROM OUTDOORS and VENT AND SUPPLY AIR SAFETY CHECK in these instructions for additional information and safety check...

Страница 21: ...mounted on the burner assembly If the temperature around the burner exceeds the set point the ignition control and the gas valve are de energized The operation of this control indicates a malfunction...

Страница 22: ...m Source 1 which has the following items 1 12 30 cm length x 1 8 0 3 cm diameter tubing 2 pieces of 4 10 cm length x 1 8 0 3 cm diameter tubing 1 5 16 0 8 cm tee 1 5 16 0 8 cm x 1 8 3 175 mm reducing...

Страница 23: ...at the gas meter times a barometric pressure and temperature correction factor of 0 960 times 3600 then divided by the time it took to measure 0 10 m3 of gas from the gas meter For Propane LP Gas mul...

Страница 24: ...h low and high have been calibrated at the factory Additional pressure adjustment should not be necessary If adjustment is necessary set to the following specifications After adjustment check for gas...

Страница 25: ...eration Start the system by setting the thermostat above the room temperature Observe the system s response Then use the troubleshooting section in this manual to check the system s operation FURNACE...

Страница 26: ...mit switch has opened its normally closed contacts and has remained open for more than five minutes This condition is usually caused by a failed blower motor or blower wheel 12 RED FLASHES This code i...

Страница 27: ...the difference in ESP values in the table 0 60 w c 150 Pa 0 50 w c 125 Pa to obtain a percentage 0 58 0 50 0 60 0 50 0 8 Multiply percentage by airflow difference to obtain airflow reduction 0 8 X 70...

Страница 28: ...50 1440 1430 1390 1360 1310 1270 1220 1150 41 6 41 1 40 8 40 5 39 4 38 5 37 1 36 0 34 5 32 6 Low 1260 1260 1260 1260 1250 1200 1150 1110 1070 1010 35 7 35 7 35 7 35 7 35 4 34 0 32 6 31 4 30 3 28 6 80...

Страница 29: ...640 1550 1460 56 6 55 5 54 7 53 8 51 0 49 8 48 4 46 4 43 9 41 3 Medium 1440 1440 1430 1420 1400 1380 1340 1300 1220 1150 40 8 40 8 40 5 40 2 39 6 39 1 37 9 36 8 34 5 32 6 Low 1220 1230 1230 1230 1200...

Страница 30: ...272312 UIM A 0407 30 Unitary Products Group SECTION IX WIRING DIAGRAM FIGURE 31 Wiring Diagram...

Страница 31: ...272312 UIM A 0407 Unitary Products Group 31 NOTES...

Страница 32: ...t to change without notice Printed in U S A 272312 UIM A 0407 Copyright by York International Corp 2007 All rights reserved Supersedes 167185 UIM C 0806 Unitary 5005 Norman Product York OK Group Drive...

Отзывы: