C.I.B. UNIGAS
- M039213CB
36
9
in order to get the maximum oil flow rate, adjust the pressure (reading its value on the
PG
pressure gauge) without changing the air
flow rate set during the gas operation adjustments (see prevoius paragraph): checking always the combustion parameters, the
adjustment is to be performed by means of the
SV2
adjusting cam screw (see picture) when the cam has reached the high flame
position.
10 once the air and oil flow rate have been adjusted at the maximum output, go on with the point to point adjustment on the
SV2
adju-
sting cam as to reach the minimum output point: gradually move the adjusting cam in order to adjust each of the
V2
screws as to
describe the cam foil shape.
11 to change the
SV2
position set the actuator on the manual mode (MAN), turn the adjusting cam
SV2
and set again the actuator to
the AUTO mode to lock the adjusting cam;
12 act on the
V2
screw that mathces the bearings referring to the adjusting cam position;
13 to adjust the next screw, set again the actuator mode to MAN, turn the adjusting cam and set the actuator to AUTO mode to lock
the adjusting cam on the next screw; adjust it and go on this way to adjust all the screws in order to set the cam foil shape, accor-
ding to the combustion values read.
14 Once the cam foil shape is defined, reconnect the
TAB
thermostat reconnecting the wire to the terminal no.6 or setting the RWF40
burner modulator to AUTO or the CMF switch to 3 (only for fully-modulating burner).
15 Turn the burner off then start it up again.
16 Once the pre-purge time comes to end, drive the burner to the high flame stage by the
TAB
thermostat: check the combustion
values;
17 drive the burner to low flame, if necessary adjust the low flame size (output) by inserting a screwdriver on the slot
F
to move the
BF2
cam.
18 The low flame position must never match the ignition position that is why cam
BF2
must be set 20°- 30° more than the ignition position.
19 Turn the burner off; then start it up again. If the adjustment is not correct, repeat the previous steps.
Fig. 25
Fig. 26
SV1
V1
SV2
RP
PG
SC
V2
Pressure gauge port
RP
PG
V2
SV2
BF2
F