background image

4

 

 

STEP 9:

  Once the batteries and solar panels 

are all connected and wired to the Large 

Green Connector, Disconnect PV+ wire and 

plug the connector to the MPPT Solar Control-

ler until the connector latches click into place. 

The Battery Charging LED should light up for 

about 60 seconds. Now connect PV+ to the 

green connector. 

 

Warning: 

Battery should always be con-

nected first and disconnected last from 

the controller.

 

STEP 10:  

Plug the temperature sensor to the Temp Sensor input on 

the MPPT Solar Controller.  Refer to the TPDIN

-

SC48

-

20 instruction 

manual for setup and operation of the MPPT Solar Controller.

 

STEP 11: 

The vent fan is capable of running at 24 or 48V. Connect to 

the controller Aux output or directly to the batteries. 

 

STEP 12:  

Tighten the cable glands on the wires to make weatherproof 

connections. Plug unused holes using the supplied hole plugs.  To plug 

an unused cable gland, cut a short piece of wire, insert into the cable 

gland and tighten. If desired, attach the enclosure to the solar mount 

pole using chain or cable for security.

 

STEP 13: 

 You may want to put a fine screen over the vent holes on 

either end of the enclosure to keep out insects. Window screen works 

well. Be sure to secure all cables so they won

t move in the wind. All 

cable connectors will be protected by being located under the solar 

panels.

 

 

TECH CORNER

 

 

Additional Information you may find useful

 

1.

 CONTROLLER: 

The MPPT controller with 7 port PoE gigabit switch 

is designed for use with 48V battery and 48V solar panels. It has a set-

table low voltage disconnect function to shut down the load power when 

the battery voltage drops below a pre

-

defined level. Maximum solar cur-

rent is 20A. You will need to access the web interface of the controller 

to setup the various built

-

in functions. Refer to the controller user guide 

which came with the controller.

 

2.

 Fuse:

 There is a fuse in

-

line in the battery cables. If fuse is blown 

there was some sort of short in the battery connection and the controller 

will appear dead. Replace with 3AG 6.3 x 32mm 20A Slo

-

Blo fuse.. 

 

3.

 

VENTING: 

The  enclosure  is  vented  thru  a  thermostatically  (45C) 

 

Содержание RemotePro RPAL48

Страница 1: ...Port 48V 20A MPPT Solar Automated Alerts Removable Connec tions Safety For your own protection follow these safety rules Perform as many functions as possible on the ground Do not attempt to install on a rainy windy or snowy day or if there is ice or snow accumulation at the install site or if the site is wet Make sure there are no people pets etc below if you are working on a roof or ladder Recom...

Страница 2: ...teries STEP 4 Place battery box under solar panels Install 4 batteries in the box Use handles to lower batteries into the box Remove the battery fuse from the battery cable before proceeding Connect all 4 batter ies in series configuration Positive to Negative to Positive STEP 5 Install DIN rail to enclosure using the two screws provided Install MPPT solar controller to DIN Rail Remove the Large G...

Страница 3: ...can shorten the cables as necessary for a cleaner install You can also lengthen the cables by adding additional lengths of 12AWG cable Please note that the longer the cable the more cable loss you will see STEP 8 Connect the solar panels in series Positive to Negative by plugging the positive from panel 1 to the negative of panel 2 and then connect the long 20 solar cable to the remaining positive...

Страница 4: ...n If desired attach the enclosure to the solar mount pole using chain or cable for security STEP 13 You may want to put a fine screen over the vent holes on either end of the enclosure to keep out insects Window screen works well Be sure to secure all cables so they won t move in the wind All cable connectors will be protected by being located under the solar panels TECH CORNER Additional Informat...

Страница 5: ...ry voltage drops below the level that is setup in the user interface normally around 47V and this will protect the bat tery from over discharge If batteries get completely discharged be cause the equipment was connected directly to the battery you will re duce the battery life and you will most likely need to charge them with a good quality 10A automotive battery charger Once they are back to a no...

Страница 6: ...tery cable fuse Check the controller fuse Measure battery voltage at the solar controller it should be 9V If less than 9V then batteries will need to be charged with an external charger to bring the volt age up to normal operating range of the controller NOTES ...

Страница 7: ...y Type Valve Regulated Sealed Lead Acid Pure Lead Carbon AGM Battery Life 5 Years Controller Type 48V 20A MPPT Battery Charge Control ler with 7 port Gigabit PoE switch and remote management Over discharge protection 45 8V to 47 8 settable in web interface Over discharge recovery volts 48 1V to 49 2V settable in web inter face Controller Self Consumption 3 5W Typical Enclosure Type Diamond Plate A...

Страница 8: ... replacement due to improper installation misuse poor site conditions faulty power etc Lightning or weather damage Physical damage to the external internal parts Products that have been opened altered or defaced Water damage Usage other than in accordance with instructions and the normal intended use Tycon Systems Inc 14641 S 800 W Suite A Bluffdale UT 84065 support tyconsystems com PH 801 432 000...

Отзывы: