STEP 1 – START THE GAUGE 

To turn on the gauge, press the power switch. After 

briefly displaying the model number, software version, 

and serial number, the gauge performs a self-test, 

followed by a display test. The gauge then enters a 

300-sec. warm-up then displays the 

Ready

 screen. 

 

 

STEP 2 – SET UP THE GAUGE 

SET UNITS 

The gauge can display measurement results in either 

U.S. units (pcf) or metric (SI) units (kg/m

3

 or g/cm

3

). To 

select the units, press 

SETUP

 to display the 

Setup

 

menu. Press 

5

 to display 

Options. 

Then press

 

3

 to 

display the 

Units 

menu. Select the new units using the 

corresponding number key. Then press 

ESC

 

to return 

to the 

Ready

 screen. 

SELECTING MODE 

To select the desired Mode, press the Mode button on 

the keypad. Then select the appropriate mode by 

pressing 

 1

 

 for Asphalt or 

 2

 

for Soil. 

-Mode-

 

1:   Asphal t  

2:   Soi l

 

TARGET VALUES 

To access the 

Target

 menu, press 

TARGET

. The 

gauge displays:  

-Target-

 

1:   Pr oct or  

2:   Gmb  ( Mar shal l )  

3:  

Gmm  ( Voi dl ess)

 

 

Select the target desired: Proctor for soil testing, Gmb 

for asphalt precent compaction and Gmm for %Voids 

in asphalt mode. 

To enter a new target value, press 

5

. At the prompt, 

use the number keys to enter the desired target value. 

To select a stored target value, press the number key 

that matches the displayed target value. 

After entering a new value press 

ENTER/START

. The 

gauge displays the value entered and asks if you want 

to store the value. To store the value, press 

YES

 

and 

select one of the four locations. Storing a new value in 

an occupied location will erase the old value. Press 

NO

 

if storing the value is not desired.

 

This will enable 

the value and return to the 

Ready

 screen. This value 

will remain enabled until changed or disabled. 

STEP 3 – TAKE A STANDARD COUNT 

To compensate for the source decay, adjust for 
background influences and to check proper operation 
of the gauge, take a standard count each day that the 
gauge is used. It is recommended that the standard 
count be performed at the first test site at a particular 
job site. 
Keep any other nuclear gauge or radioactive source at 

least 10 m (30 ft.) from test site. 

 

 

 

 

 

1

1

.

.

 

 

Prepare the test site.

 Place the gauge on soil, 

asphalt, or concrete material with no air gaps 
underneath. 

2

2

.

.

 

 

Press 

STD

. The gauge displays the last 

standard count. To take a new standard count, 
press 

YES

. With the gauge in the standard 

count (safe) position, press 

ENTER/START

 to 

begin the standard count. 

3

3

.

.

 

 

When prompted, 

lower the gauge handle to 

the background position

 (slightly below the 

safe position) to begin the second step of the 
standard count.  Press 

ENTER/START

 

as 

prompted. 

Troxler recommends keeping a daily log of the 

standard count results. An example log is provided in 

the appendix of the user manual. 

STEP 4 – PREPARE THE TEST SITE 

For backscatter measurements locate a smooth site 

and be sure the gauge base has good contact with the 

material surface. 

To ensure measurement accuracy, properly prepare 

the test site 

before

 taking gauge measurements. 

CAUTION 

Safety glasses must be worn during this procedure. 

1

1

.

.

 

 

For direct transmission measurements, locate a 
smooth site on the compacted material free 
from any large holes, cracks, or debris. Place 
the scraper plate on the surface and press 
down slightly or scrape lightly if needed to 
smooth the surface. 

2

2

.

.

 

 

As shown in Chapter 4 of the user manual, put 
the drill rod through the extraction tool and 
then through the guide tube on the scraper 
plate.  

3

3

.

.

 

 

Step on the scraper plate and hammer the drill 
rod to at least 50 mm (2 in.) deeper than the 
desired test depth. The drill rod increments 
include the additional depth.   

4

4

.

.

 

 

Remove the drill rod by pulling straight up on 
the extraction tool. Do not loosen the drill rod 
by moving it from side to side. Trace the plate 
to mark the test area. 

Note- Be sure no other nuclear sources (gauges) 

are within 10 m (30 ft.) of EGauge while in use. 

Note- This gauge does not require a reference 

block to take the standard count. Ensure that the 

source rod is in the SAFE position by firmly 

tapping down on the handle of the source rod. 