17
FLUE ASSEMBLY
The flue terminal pack (supplied) should contain the
following items. Check all components are present before
fitting:
1 x Flue Terminal Assembly
1 x Elbow & Sealing Plate Assembly
1 x ‘O’-Ring Seal
1 x Tube of Silicone Sealant
The flue may exit from the rear, right or left side of the boiler.
The termination point is angled, and can be rotated to enable
the combustion fumes to be directed away from areas where
they could cause a nuisance.
FITTING INSTRUCTIONS
1) Decide which direction the flue is to be pointed. Remove
the top panel and using the nuts provided, fit the
elbow/sealing plate assembly (
item 1
) onto the rubber
gasket on top of the boiler via the 4 x studs, ensuring
that the open end is pointed in the direction required.
2) Fit the ‘o’-ring seal (
item 2)
into the groove on the flue
terminal (
item 3
), ensuring that the flat, ribbed face is to
the inside.
3) Smear a thin bead of silicone sealant (supplied) around the
‘o’-ring seal and slide the terminal into the elbow from the
outside of the boiler casing, being careful to ensure that the
‘o’-ring remains in place. The rotation of the terminal should
be decided before applying the silicone sealant.
4) Place the terminal in the desired position and angle of
rotation. Ensure that a minimum distance of 50mm is kept
from the termination point to the face of the boiler casing.
5) Slide one of the sealing rubbers (
item 4
) over the terminal to
meet the boiler casing, ensuring the holes line up with those
in the casing.
6) Fit the collar plate (
item 6
) over the flue terminal and secure
to the boiler casing with the screws provided, clamping the
sealing rubber firmly in place.
7) Blank off the 2 x unused flue openings on the boiler casings
with the remaining sealing rubbers and blanking plates (
item
5
).
8) Replace the top casing and fit the terminal guard (
item 7
)
over the flue, securing in position with the screws provided.
FIG 15
FLUE ASSEMBLY
Содержание Contractor H.E. 50/90 EXTERNAL
Страница 1: ...1 H E 50 90 EXTERNAL HE 100 125 EXTERNAL OIL FIRED CENTRAL HEATING BOILER...
Страница 2: ...2...
Страница 6: ...6...
Страница 15: ...15 FIG 12 SINGLE PIPE OIL SUPPLY BOILER FIG 13 TWO PIPE OIL SUPPLY BOILER...
Страница 23: ...23...