Installation checklist
RTRA Trane Air Cooled Liquid Chiller
This list must be checked off by the installer to ensure correct installation before the unit starts up.
Unit acceptance
❏
Check for damage, if any, on transportation
❏
Check for equipment shipped against delivery slip
❏
Check lifting system
Unit positioning
❏
Remove packaging
❏
Check position of unit
❏
Check unit is level
❏
Check clearance around condenser
❏
Check clearance required for maintenance access
❏
Check position of rubber pads
Chilled water circuit
❏
Check presence of strainer ahead of evaporator
❏
Check the tightness of the water circuit
❏
Check thermometer positioning
❏
Check manometer positioning
❏
Check chilled water flow rate balancing system
❏
Check rinsing and filling of chilled water pipes
❏
Check pump operation and water flow
Electrical equipment
❏
Check direction of rotation of compressors and fan motors
❏
Check installation and rating of mains power switch/fuse
❏
Check that electrical connections comply with specification
❏
Check that electrical connections match information on manufacturer’s identification plate
❏
Check electrical connections and connections to mains power switch
❏
Water pressure switch
Ducting
❏
External pressures of air inlet and discharge ducting
General
❏
Check available cooling charge (50% of rated installation load)
❏
Check with other trades handling installation works
Comments : ...........................................................................................................................................................................
................................................................................................................................................................................................
................................................................................................................................................................................................
................................................................................................................................................................................................
................................................................................................................................................................................................
Signature : ...........................................................
Company : ........................................................................................
Order N° ...............................................................................................................................................................................
Work site : ............................................................................................................................................................................
Please return to your local Trane Service Agency