1. This furnace modulates between 40% and 100% of 

capacity, in 3% increments, every 1 minute. The 
furnace always lights at approximately 65% and 
will modulate up or down; depending on the 24VAC 
thermostat signal. Requested capacity can be seen 
in the “STATUS” section of the User Interface menu.

Note: 

Pressure Switch 1 closes at approximately 40% of 
capacity. 
Pressure Switch 2 closes at approximately 65% of 
capacity. 
Pressure Switch 3 closes at approximately 95% of 
capacity.

Thermostat call for W1 (2 stage heating thermostat)

2. R and W1 contacts close signaling the control board 

(IFC) to run its self- check routine. After the control 
has verified that all safeties are closed and PS1, 
PS2, and PS3 pressure switch contacts are open, the 
IFC signals the variable speed inducer drive to start 
the vent motor at the speed needed to close pressure 
switches PS1 and PS2.

Note:
The furnace lights at approximately 65% of capacity

.

3. PS1 and PS2 close.
4. The IFC receives a 24 VAC signal from PS1 and PS2 

when they close. This verifies the vent motor is 
moving the correct amount of combustion air through 
the furnace and the vent system.

5. IFC starts the hot surface ignitor learning routine 

warm-up time cycle.

6. IFC turns on the gas valve. Trial time for ignition is 5 

seconds.

7. The IFC verifies ignition by the flame current sensing 

method. If a flame is not detected, the IFC will cycle 
the furnace three times to try and verify a flame. If no 
flame is detected, the IFC will lockout for one hour. 
The IFC will send an alert code to the communicating 
comfort control (ERR 22) and User Interface (RETRY 
LO) as well as flash its Red alert LED two times 
repeatedly.

8. If a flame is detected, the IFC will start the heat 

exchanger warm-up time delay for the indoor blower.

9. “IGNITION” will now be displayed in the “STATUS” 

section of the User Interface menu.

10. After 45 seconds, the IFC signals the indoor blower 

motor to run at the programmed ignition sequence 
speed.

11. The IFC then signals the variable speed inducer 

motor drive board to ramp down to the corresponding 
speed to keep PS1 closed. The reduction of the vent 
motor speed in steps allows the gas flow through the 
gas valve to also be reduced in steps, decreasing the 
chance of burner flame out. The W1 heating capacity 
is 40%. The IFC will also decrease the indoor blower 
motor speed. 

Thermostat call for W2 after W1

12. R and W2 thermostat contacts close signaling a call 

for W2 heat. The IFC then signals the variable speed 
inducer drive to ramp up the vent motor allowing flow 
through the gas valve to also be increased in 3% 
steps. 

13. If the call for W2 remains, this 3% increase will be 

repeated every 1 minute until the capacity requested 
is 100%. The IFC will also increase the indoor blower 
motor speed in appropriate steps. 

W2 satisfied, W1 still called for

14. R and W2 thermostat contacts open signaling that W2 

heating requirements have been satisfied. The IFC 
will signal the variable speed vent motor to slow down 
to its learned W1 speed. The gas valve will reduce 
the gas flow to 40% capacity and the indoor blower 
motor speed will be reduced. 

W1 satisfied 

15. R and W1 thermostat contacts open signaling that W1 

heating requirements have been satisfied. The gas 
valve will be de-energized and gas flow will cease. 
The variable speed vent motor will de-energize 
approximately after a 5 second post purge. The 
indoor blower motor will be de-energized after the fan 
off delay period has ended. (The indoor blower heat 
fan off delay is field selectable and can be adjusted 
using the User Interface menu. It is factory set at 100 
seconds but can be set to 60, 140, or 180 seconds)

Thermostat call for heat (1 stage heating thermostat)

Note: The inter-stage delay is field selectable and can 
be adjusted through the User interface menu. It is fac-
tory set at 0 minutes but can be adjusted to 5, 10, or 
15 minutes. This option can help optimize the furnace 
to try to satisfy the heating requirement during low 
heating load conditions. 

16. W1 and W2 must be jumpered at the IFC. R and 

W1 contacts close signaling the control board (IFC) 
to run its self- check routine. After the control has 
verified that all safeties are closed and PS1, PS2, 
and PS3 pressure switch contacts are open, the IFC 
signals the variable speed inducer drive to start the 
vent motor at the speed needed to close pressure 
switches PS1 and PS2.

Note:
The furnace lights at approximately 65% of capacity

.

17. PS1 and PS2 close.
18. The IFC receives a 24 VAC signal from PS1 and 

PS2 when they close. This verifies the vent motor is 
moving the correct amount of combustion air through 
the furnace and the vent system.

19. IFC starts the hot surface ignitor learning routine 

warm-up time cycle.

20. IFC turns on the gas valve. Trial time for ignition is 5 

seconds.

21. The IFC verifies ignition by the flame current sensing 

method. If a flame is not detected, the IFC will cycle 

Содержание DHMB060BCV3VB

Страница 1: ...gnate a degree or level of seriousness associated with a particular hazard 2 The signal words for safety markings are WARNING and CAUTION 3 a WARNING indicates a potentially hazardous situation which...

Страница 2: ...their previous condition of use WARNING Failure to follow safety warnings exactly could result in a fire or explosion causing property damage personal injury or loss of life Do not store or use gasol...

Страница 3: ...ks with an open flame Use a commercially available soap solution made specifically for the detection of leaks to check all connections as specified in the Gas Piping section starting on page 34 6 Alwa...

Страница 4: ...NT ALTITUDES REFER TO THE VENT LENGTH TABLE FOR PROPER APPLICATION UHM ACV OUTLINE DRAWING ALL DIMENSIONS ARE IN INCHES MODEL SEE NOTE 1 DIM A DIM B DIM C DIM D DIM E DIM F UHMB060ACV3VB UHMB080ACV3VB...

Страница 5: ...ACV DOWNFLOW HORIZONTAL OUTLINE DRAWING ALL DIMENSIONS ARE IN INCHES MODEL SEE NOTE 1 DIM A DIM B DIM C DIM D DHMB060BCV3VB DHMB080ACV3VB 17 1 2 2 1 4 16 1 4 16 DHMC100ACV4VB 21 2 1 2 19 3 4 19 1 2 DH...

Страница 6: ...ty to the furnace must be provided Any access door or panel must permit removal of the largest component 4 Are there at least 3 inches of clearance between the furnace combustion air openings in the f...

Страница 7: ...urnace installation in an attic should be on a service platform large enough to allow for proper clearances on all sides and service access to the front of the furnace See Figure 5 Clearance Tables on...

Страница 8: ...mately 4 6 inches to allow clearance for the condensate drain to exit the cabinet in the horizontal position The horizontal furnace may also be suspended from the joists using all thread rods with a s...

Страница 9: ...ed space shall be provided with two permanent openings one commencing within 12 inches of the top and one commencing within 12 inches of the bottom of the enclosure The openings shall communicate dire...

Страница 10: ...while installing or servicing Personal injury may result Where there is no complete return duct system the return connection must be run full size from the furnace to a location outside the utility r...

Страница 11: ...left side or right side return air inlet Some filters may need to be trimmed for side or bottom filter use TABLE 4 NOTE For upflow 5 ton airflow models where the airflow requirement exceeds 1800 CFM...

Страница 12: ...RNATE FILTER RACK INSTALLATION FOR SIDE RETURN AIR ON UPFLOW FURNACES LEFT OR RIGHT BAYRACK960 NOTE The filter rack installation is not allowed for right side return on the following models UHMB060ACV...

Страница 13: ...ance holes with a 3 16 drill Bottom return holes are pre drilled Attach clip to bottom channel and rear of unit with screws provided for bottom return 2 Install the clips in front and rear of the desi...

Страница 14: ...may be A or T TABLE 7 LOCATING FILTER RETAINER BRACKETS IN DUCTWORK CABINET WIDTH RETURN DUCT WIDTH DIMENSION A DIMENSION B FILTER BRACKET LOCATION 17 1 2 16 1 4 15 14 14 3 8 21 19 3 4 19 1 2 14 13 1...

Страница 15: ...h appliance connected to the venting system being placed into operation could result in carbon monoxide poisoning or death The following steps shall be followed for each appliance connected to the ven...

Страница 16: ...OR DOWNFLOW HORIZONTAL NOTE See Figures 23 24 In horizontal venting when the factory supplied off set 2X3 reducing coupling is used for 3 vent pipe installation make sure the marking Top is located o...

Страница 17: ...throughout Listed in Table 9 are materials that meet these requirements The materials listed are various grades of PVC and ABS plastic PIPE JOINTS All joints must be fastened and sealed to prevent esc...

Страница 18: ...NT PIPE with RTV sealant Seal INLET AIR PIPE with RTV sealant Front of Furnace VENT AND INLET AIR CONNECTIONS g 5 Wipe all excess cement from the joint with a rag Allow 15 minutes before handling Cure...

Страница 19: ...r T Last two digits may be A thru Z 1 Minimum vent length for all models 3 horizontal or 3 vertical 2 DO NOT MIX PIPE DIAMETERS IN THE SAME LENGTH OF PIPE OUTSIDE THE FURNACE CABINET Except adapters a...

Страница 20: ...from freezing then the space meets the condition of a heated space VENTING THROUGH THE ROOF When penetrating roof with a 2 PVC Vent Pipe a 2 electrical conduit flashing may be used for a weather tigh...

Страница 21: ...n direct vent Installation must con form to national state and local codes The vent inlet terminals must be located at least 12 minimum above normally expected snow accumulation level See Figure 29 Av...

Страница 22: ...period a battery operated carbon monoxide detector with an alarm shall be installed 2 APPROVED CARBON MONOXIDE DETECTORS Each carbon monoxide detector as required in accordance with the above provisio...

Страница 23: ...ied locally For Canadian applications only IPEX 196006 IPEX 081216 IPEX 081218 and IPEX 081219 may be used for horizontal vent terminations HORIZONTAL VENT CLEARANCES See clearance tables 11 and 12 on...

Страница 24: ...allation Instructions Table 12 Direct Vent Terminal Clearances Canadian Installations US Installations A Clearance above grade veranda porch deck or balcony 12 inches 30 cm 12 inches 30 cm B Clearance...

Страница 25: ...tch 1 4 Inch Per Foot CLEARANCE 0 ACCEPTABLE FOR PVC VENT PIPE 1 ACCEPTABLE FOR TYPE 29 4C STAINLESS STEEL VENT PIPE 12 MINIMUM ABOVE NORMALLY EXPECTED SNOW ACCUMULATION LEVEL 6 IN MIN TO JOINT x COUP...

Страница 26: ...AVENTA VERTICAL REMOVE RIBS FROM CAP COMBUSTION AIR ROOF BOOT FIELD SUPPLIED COMBUSTION AIR VENT ELBOW FIELD SUPPLIED MAINTAIN 12 IN MINIMUM CLEARANCE ABOVE HIGHEST ANTICIPATED SNOW LEVEL MAXIMUM OF 2...

Страница 27: ...TAL VENTING TO VERTICAL VENTING 6 IN MIN SEE CAUTION STAINLESS STEEL VENT CAP OPTIONAL SUPPORT THE SINGLE WALL FLUE PIPE AND CENTER IT IN THE CHIMNEY OPENING WITH ANGLES AS SHOWN OR ANOTHER EQUIVALENT...

Страница 28: ...cal source is utilized The integrated furnace control is polarity sensitive The hot leg of the 120V power supply must be connected to the Black power lead as indicated on the wiring diagram Provision...

Страница 29: ...taller s Guide FIELD WIRING DIAGRAMS 41B Communicating Indoor Unit with Communicating Comfort Control and 24VAC Single Stage Cooling 41C 24 VAC Mode Indoor Unit with 24 VAC Comfort Control and 24VAC S...

Страница 30: ...er s Guide 41D 24 VAC Mode Indoor Unit with 24 VAC Comfort Control and 24VAC 2 Stage or 2 Step Cooling 41E 24 VAC Mode Indoor Unit with 24 VAC Comfort Control and 24VAC Single Stage Heat Pump Field Wi...

Страница 31: ...ween R and BK on the circuit board must be cut if an optional humidistat is installed HUMIDISTAT HOOKUP 24 V ONLY If an optional humidistat for humidity control in cooling is used the factory installe...

Страница 32: ...e second ary heat exchanger drain connection to prevent water from damaging furnace controls if the primary drain outlet plugs up Where the furnace is installed above a finished ceiling the primary dr...

Страница 33: ...osition into the other drain tap of the inducer which is located 90 clockwise around the inducer Move the cap from that drain tap to the unused drain tap On upflow units plug the hole in the blower de...

Страница 34: ...SONAL INJURY OR DEATH CAUTION Use a backup wrench on the Gas Valve when installing Gas Piping to prevent damage to the Gas Valve and Manifold Assembly The upflow horizontal furnace is shipped standard...

Страница 35: ...MANUAL SHUT OFF AUTOMATIC GAS VALVE WITH MANUAL SHUT OFF DRIP LEG DRIP LEG DRIP LEG DRIP LEG IMPORTANT A sediment trap must be installed in the gas line be fore the furnace gas valve The sed iment tr...

Страница 36: ...t for one revolution Table 18 shows the flow rate in cubic feet per hour for a measured time of one revolution for a meter on which one revolution indicates 2 cubic feet per hour of gas flow For other...

Страница 37: ...33 218 54 133 90 80 13 555 34 212 55 131 92 78 14 514 35 206 56 129 94 76 15 480 36 200 57 126 96 75 16 450 37 195 58 124 98 73 17 424 38 189 59 122 100 72 18 400 39 185 60 120 104 69 19 379 40 180 62...

Страница 38: ...sure Switch PS 3 Pressure Switch PS 2 Negative Control Pressure Post Positive Control Pressure Post Modulating Gas Valve Orifice in H fitting must be pointing away from PS1 VACUUM HOSE ROUTING R To Pr...

Страница 39: ...leaned annually using brushes and vacuum cleaner for any gas that might have escaped to dissipate LP Gas being heavier than air may require forced ventilation Turn the toggle switch on the Gas Valve i...

Страница 40: ...n to scroll through setup menu Push ENTER to make selection Viewing Window User Interface pictured above adjusts Variable Speed Airflow options and is used for custom setup of Furnace operations See m...

Страница 41: ...500 1600 A TDHMD120 1850 1850 2040 1660 1760 Information Menu Information Options MODEL NUMBER MODEL A TUHM SERIAL NUMBER SERIAL SW REV NUMBER SW REV NUMBER SYSTEM STATUS SYSTEM STATUS OFF REQUESTED C...

Страница 42: ...1400 1400 1610 1120 1260 A TUHMC100 1620 1620 1790 1460 1540 CONT FAN CFM CONT FAN CFM A TUHMD120 1890 1890 2000 1700 1790 50 50 75 100 25 A TDHMB060 1040 1040 1160 900 950 A TDHMB080 1400 1400 1610...

Страница 43: ...drive board to ramp down to that corresponding demand speed The reduction of the vent motor speed in steps allows the gas flow through the gas valve to also be reduced in steps decreasing the chance...

Страница 44: ...or blower motor speed Thermostat call for W2 after W1 12 R and W2 thermostat contacts close signaling a call for W2 heat The IFC then signals the variable speed inducer drive to ramp up the vent motor...

Страница 45: ...ent motor to ramp up The increase of the vent motor speed allows the gas flow through the gas valve to also be increased in 3 steps This 3 increase will be repeated every 1 minute until the capacity r...

Страница 46: ...N and push the Enter button e When asked Are You Sure select Yes and push the Enter button f The furnace will now begin the ignition sequence g If pressure switch 1 2 learning routines have not been p...

Страница 47: ...ustable 10 0 0 5 100 2 1 0 5 Not Adjustable 10 0 0 5 Downflow 120 2 1 0 5 Not Adjustable 10 0 0 5 Upflow 120 2 9 0 5 Not Adjustable 10 0 0 5 For upflow 120KBTU hr model 1st stage is 45 Manifold pressu...

Страница 48: ...arning routine is complete and that the heat rise is stable j Read the 100 manifold pressure k If needed remove the high heat manifold adjustment cover and adjust to obtain the correct manifold pres s...

Страница 49: ...E will now be displayed Press the Enter button STAGE and OFF OFF will now be displayed First or Second heat stage must be selected Use the or arrows to select the stage of heat wanted and then push th...

Страница 50: ...ion being asked use the or arrows to select the YES and then press the ENTER button Are you Sure and NO NO will now be displayed With a NO NO question being asked use the or arrows to select the YES a...

Страница 51: ...e for 100 high heat until it receives a call for 100 high heat PS 3 INDUCER LEARNING ROUTINE When the furnace IFC receives a digital signal for 100 high heat from the comfort control it will begin the...

Страница 52: ...Control to a temperature higher than the in dicated room temperature to start the furnace Restrict the airflow by blocking the return air disconnecting the Indoor Blower may trip the Inducer Limit Wh...

Страница 53: ...g Cycle or flame is not present at the sensor the Integrated Furnace Control IFC will close the Gas Valve The Integrated Furnace Control will then recycle the Ignition Sequence If Ignition is not achi...

Страница 54: ...e displayed on the User Interface menu using a descriptive text message and on the comfort control display using an alert code number A com plete list of the alert codes is included with the comfort c...

Страница 55: ...Failure Communication Message has been detected while configured for 24V Mode Solid ON Device count CNTRL FAULT ERR 18 18 Control Failure Internal control failure None Device count TWIN ERROR N A 19...

Страница 56: ...ta improvement and reserves the right to change design and specifications without notice Trane 6200 Troup Highway Tyler TX 75707 For more information contact your local dealer distributor Literature O...

Отзывы: