CHECKOUT PROCEDURES
After installation has been completed, it is recommended that the Air Handler be checked against the following
checklist.
1.Make sure power is “OFF” at power disconnect
switch ...............................................................................
.................................................................................... [ ]
2.Check all field wiring for tight connections. See that
grounding of unit is in accord with code .................. [ ]
3.Make sure unit suspension (if used) is secure
and that there are no tools or loose debris in,
around or on top of the unit ...................................... [ ]
4.Check all duct outlets; they must be open
and unrestricted ........................................................ [ ]
5.Check drain lines and be sure all joints are tight [ ]
6.Make sure secondary drain pan is installed ......... [ ]
7.Check power supply for correct requirements
per unit nameplate .................................................... [ ]
8.Check filters for proper size. Inform owner of
proper procedure for removal and reinstallation .... [ ]
9.Energize the system and carefully observe its opera-
tion; make any necessary adjustment...................... [ ]
10.Instruct owner, engineer (if possible) on proper
operating procedure and leave Use and Care
Manual with owner ................................................... [ ]
SUPPLEMENTARY HEATERS CHECKOUT PROCEDURES
IF a heater is USED, see "limitations and recommendations"
to determine if the heater requires a SPECIAL CIRCUIT.
1. Be sure the disconnect switch is “OFF”, and safety label (if any) is attached ............................ [ ]
2. Check on field wiring for tight connections and grounding according to codes .......................... [ ]
3. Check circuit protection for proper size per nameplate specifications ........................................ [ ]
4. Check control box panel — in place and secured .......................................................................... [ ]
NOTE:
OPERATION OF HEATERS MUST BE CHECKED DURING THE OPERATIONAL CHECK OF THE TOTAL SYSTEM.
I. CHECKOUT PROCEDURE
1. Check the Air Handler installation in accordance with this instruction.
2. “Operational Procedure” for the system installation can be found in the outdoor unit installer guide and will be
compatible with this Air Handler.