TRAK Machine Tools
Site Preparation Guide TRAK VMC5
F16467-53 Rev 050520
Page 2 of 7
Figure 1
–
Front View of Machine
Figure 2
Side View of Machine
Страница 1: ...he installation and service manual for additional information Make sure to follow our grounding recommendations The machine must have air hooked up We strongly recommend that a water separator or air...
Страница 2: ...TRAK Machine Tools Site Preparation Guide TRAK VMC5 F16467 53 Rev 050520 Page 2 of 7 Figure 1 Front View of Machine Figure 2 Side View of Machine...
Страница 3: ...TRAK Machine Tools Site Preparation Guide TRAK VMC5 F16467 53 Rev 050520 Page 3 of 7 Figure 3 Lifting the VMC Figure 4 Lifting the VMC...
Страница 4: ...TRAK Machine Tools Site Preparation Guide TRAK VMC5 F16467 53 Rev 050520 Page 4 of 7 Figure 5 Lifting the VMC Figure 6 Leveling Pad Locations...
Страница 5: ...TRAK Machine Tools Site Preparation Guide TRAK VMC5 F16467 53 Rev 050520 Page 5 of 7 Figure 7 Lifting Machine with Straps Figure 8 Lifting Machine Eye Bolts on Top of Column...
Страница 6: ...figure 9 Figure 9 Connect the Ground Wire Machine Grounding It is strongly recommended that the machine be earth grounded A dedicated copper rod 8 feet or so in length should be driven into the ground...
Страница 7: ...TRAK Machine Tools Site Preparation Guide TRAK VMC5 F16467 53 Rev 050520 Page 7 of 7 Figure 10 Exit Location for Ground Wire to Copper Rod...