Electrical Connections 

Main Power to the Machine Connections 

The 3 phase 208 voltage (200 

 240 V is acceptable) is connected to L1, L2 and L3 at the main power switch inside 

the electrical box. Connect the ground wire as shown in the figure 9.   

 

Figure 9 

 Connect the Ground Wire 

Machine Grounding 

It is strongly recommended that the machine be earth grounded. A dedicated copper rod 8 feet or so in length 

should be driven into the ground near the TMC. A ground wire should then be run from the location shown in figure 
9. The copper wire should exit the electrical cabinet in the lower right-hand corner as shown in figure 10. Make sure 

the foam where the copper wire goes through seals the cabinet from external debris. The wire should be 6 gage in 
size.  

 
 
 
 
 

 

 
 
 
 
 
 
 
 
 
 

 
 