Torque X-CREATE Скачать руководство пользователя страница 8

45.08in

1145mm

27.80in

706mm

6.89in

175mm

6.89in

175mm

B

ANCHORING INSTRUCTIONS

ANCHORING DIMENSIONS FOR BRIDGE SYSTEMS

X-Create Bridge Systems are expandable in 2 foot increments.  Shown above is the XCB-

2M-13 which is a 13 foot bridge system.  The distance for B on this system is:
  

B = 117.29 in (2979 mm) 

For longer Bridge Systems, simply add 24 inches (610 mm) per 2 foot increase in length to 

the 

B

 dimension.

8

BRIDGE SPACE SYSTEMS

Содержание X-CREATE

Страница 1: ...FACE OF SUITABLE CONSTRUCTION FAILURE TO TAKE PROPER CARE IN SITE SELECTION ASSEMBLY OR INSTALLATION CAN LEAD TO SERIOUS PERSONAL INJURY AND PROPERTY DAMAGE Electrical wires water pipes etc can be running underneath a floor so understand what is below before drilling Read these instructions carefully before proceeding and follow the installation directions carefully to minimize the risk of injury ...

Страница 2: ...e the floor surface APPROVED ANCHORING SPECIFICATIONS Concrete Floor 3 inch thick 3 000 psi or greater Minimum anchor embedment depth 2 1 2 inches Anchor option 1 3 8 to1 2 inch diameter x 3 inch Internally threaded drop in Anchor Grade 5 or higher Anchor Option 2 3 8 to1 2 inch diameter x 3 inch externally threaded concrete anchor Note Read instructions included with the specific anchors used to ...

Страница 3: ...REQUIRED TOOLS AND HARDWARE FOR ANCHORING TO CONCRETE FLOORS Hammer Drill ANSI Masonary drill bit Reference anchors for correct size 3 8 x 3 Concrete anchors 3 8 Washers Level Socket Wrench and Socket 3 ...

Страница 4: ...e floor is covered with padded carpet or rubber it is recommended that cutouts be made around the base plates so that the uprights can be mounted directly to the floor This will ensure that the system is stable and will reduce shear forces on the anchors 4 Each X Create upright provides eight anchoring locations In every upright the front two and rear two holes are required to have anchors install...

Страница 5: ...ght place a piece of cardboard between the drill casing and the upright 2 Vacuum all concrete dust from the hole Failure to remove all concrete dust may prevent the anchor from going in all the way 3 Using a socket wrench tighten a concrete bolt and washer half way in 4 Repeat the operation to the remaining anchoring holes in the upright 5 Perform this procedure one upright at a time pausing to en...

Страница 6: ... the specifications for the hardware being used 8 Install the front and rear rubber boots on each upright using four socket head bolts and four washers 6 After completing and before using check that the all of the anchoring bolts and the frame bolts are properly tightened Test the system by having multiple people push it up and away from themselves to ensure that the frame is securely fixed to the...

Страница 7: ... a small gap is needed between the wall and the rear base plate to allow room for the rubber boot For this situation A 1 125 in 28 6 mm or greater For systems that include the Dip Attachment or Plyo Attachment XCREATE DA or XCREATE PS on either end of the system it is advantageous to allow slightly more room for hand and body clearance during movements For this situation A 5 25 in 133 4 mm or grea...

Страница 8: ... SYSTEMS X Create Bridge Systems are expandable in 2 foot increments Shown above is the XCB 2M 13 which is a 13 foot bridge system The distance for B on this system is B 117 29 in 2979 mm For longer Bridge Systems simply add 24 inches 610 mm per 2 foot increase in length to the B dimension 8 BRIDGE SPACE SYSTEMS ...