2
Installing the Drive Shaft to
the Blower Gear Box Shaft
Parts needed for this procedure:
1
Drive shaft assembly
1
Roll pin
2
Bolt, 5/16 x 1-3/4 inch
2
Locknut, 5/16 inch
Procedure
1.
Remove the cable tie securing the drive shaft
to the shipping crate.
2.
Slide the drive shaft onto the gear box shaft.
3.
Align the mounting holes in the gear box shaft
with the holes in the drive shaft and slide them
together.
g023911
Figure 9
1.
Roll pin
4.
Bolts, 5/16 x 1-3/4 inch
2.
Safety chains
5.
Locknuts, 5/16 inch
3.
Drive shaft
6.
Gear box shaft
4.
Secure the assembly with a roll pin (
).
5.
Secure the drive shaft to the gear box shaft with
2 bolts (5/16 x 1-3/4 inch) and 2 locknuts (5/16
inch) (
6.
Torque the bolts to 18 to 25 N∙m (175 to 225
in-lb).
7.
Remove the cable tie that is keeping the drive
shaft together
8.
Secure the safety chain to the blower frame
(
).
3
Installing the Mounting
Plate to the Debris Blower
Frame
Parts needed for this procedure:
1
Mounting plate
4
Bolt, 1/2 x 1-1/4 inches
4
Locknut, 1/2 inch
Procedure
1.
Remove the bolts securing the mounting plate to
the crate (
g021682
Figure 10
1.
Mounting plate
2.
Install the mounting plate to debris blower frame
with 4 bolts (1/2 x 1-1/4 inch) and 4 locknuts (1/2
inch) (
Note:
Use the lower set of holes on each side
of the mounting plate.
8