7
have to pass through the hole in opener base.
3.
Pour concrete and before it starts to harden,
check that it is parallel to the gate leaf and
perfectly level.
4.
The four anchor bolts must be set into the
concrete when it is poured, make sure the
position of anchor bolts was placed according
to the position of mounting holes on the opener
base before concrete become harden.
5.
Mount the opener to the concrete Pad. It's
only temporary installation. Further adjustment
will be required when install the rack.
Manual Operation
You can open the gate by manual when power
failure. And the opener should be put in the
manual (emergency release) position before
fitting the rack, installing the opener and limit
switch. The process is as follows:
1) Take off the rubber stopple.
2) Insert the Release Key
(
provided
)
and turn it in counter-clockwise 180° to disengage the clutch
between the gear shaft and power output. Now the opener is in the manual operation.
Fit the Plastic Rack Reinforced with Steel
1. Start with gate in closed position
2. Prepare the plastic rack (you can order extra rack from dealer if necessary).
3. Put one end of rack section on the gear of opener as a temporary support.
Make rack level and mark the rack’s mounting holes
(four holes for light duty or six holes for heavy duty)
on the gate.
4. Fit the rack by self-threading screws. This kind of plastic rack is quieter and allows height adjustments to
be made even after it has been fixed. Please keep 1.0mm space between the rack and the gear to avoid the
weight of the gate effect on the opener.
Содержание RK700
Страница 6: ...3 In sake of safety a positive stop must be mounted on the two end of ground track...
Страница 19: ...16...
Страница 20: ...17...