Hanger Brackets
Top View
Side View
DLSC-IOM-8.0
Installation – General
Installing the Unit
Follow the procedures below to install the unit properly.
Refer to submittal
for specific unit dimensions and
mounting hole locations.
Install horizontal units suspended from the ceiling using metal
straps or the optional Hanging Brackets located on the top of the
unit. The hanger holes allow a maximum shank size of 1/2-inch
diameter threaded rods or lag screws (installer provided).
Note:
Follow the requirements of National Fire Protection
Association (NFPA) Standard 90A or 90B, concerning the use of
concealed ceiling spaces as return air plenums.
Follow the installation procedure below.
1. Prepare the ceiling opening for recessed units. Reference
the unit submittals for dimensions.
2. Position and install the suspension rods or a suspension
device (supplied by installer) according to the unit model and
size in submittal
4. Level the unit by referencing the chassis end panels.
Adjust the suspension device.
5. Complete piping and wiring connections, in addition to any
necessary ductwork as instructed in the following sections.
6. Install the bottom panel before starting the unit.
Motor Overload!
All unit panels and filters must be in place prior to unit
startup. Failure to have panels and filters in place may cause
motor overload.
Electrical Wiring!
Do not allow electrical wire to fall between the unit and
installation surface. Failure to comply may result in
electrical shorts or difficulty accessing wires.
NOTICE
NOTICE