7. Maintenance
7.1. Change of the tensioning wheel
Loosen the 3 fastening screws
(10)
and
remove the bearing plate
(9)
. The
tensioning wheel
(42/55)
can be
accessed and removed from the
transport shaft.
Mounting in reverse order.
7.2. Setting the clearance
After the installation of the new
tensioning wheel
(42/55)
the clearance
between wheel and guide plate
(40)
must be checked and, if required,
readjusted.
Setting is performed by means of the
setting screw
(38)
. For that purpose,
loosen the counternut
(39)
.
The clearance between the tensioning
wheel and the guide plate should
be
0,2 mm
.
7.3. Cleaning and maintenance
Dirt and abrasion impair the function of the units.
Therefore, all units should be air-cleaned with compressed air in the area of the strap
guidance, notching cutters, tensioning wheel and joints after being used und, following
that, be wetted with resin-free thin spray oil.
Tool inspection!
Perform a
daily
visual inspection of the outside of the unit. The early detection of
damaged parts extends the life of the unit. Replace all damaged parts
immediately
with Original TITAN spare parts.
H365 EU 24/12
Содержание DPZ-L
Страница 14: ...PR33 DPZ L 14 63 8 Konformit tserkl rungen H365 EU 39 12...
Страница 15: ...PR33 DPZ L 15 63 H365 EU 24 12...
Страница 34: ...PR33 DPZ L 34 63 8 Declarations of conformity of the machinery H365 EU 39 12...
Страница 35: ...PR33 DPZ L 35 63 H365 EU 07 10 H365 EU 24 12...
Страница 54: ...PR33 DPZ L 54 63 8 D claration de conformit H365 EU 39 12...
Страница 55: ...PR33 DPZ L 55 63 H365 EU 24 12...