background image

EI Automatic Transfer Switch (ATS)

2. Installation

1. General Information

3. Electrical connections

Conductor Schedule

Conductor

Qty

Type

Size

Grid

4

Min. 90°C rated, insulated
(or bare-EGC conductors),

copper, solid or stranded

(not fine stranded)

L1, L2, N: 4-4/0 AWG,

EGC: 6-1/0 AWG

Load

4

L1, L2, N: 1/0-4/0 AWG,

EGC: 6-1/0 AWG

Inverter

4

L1, L2, N: 8-6 AWG,

EGC: 8 AWG

Communications

1

RS485 shielded, twisted

pair (2-wire)

24 AWG

Quick Start Guide - TSS-200-US

Pg 1 of 3

1.

This document is for quick guidance only. For details, please refer to the Energy Intelligence (EI) ATS Installation & Operations Manual.

2.

Damage caused by failure to follow the contents of the EI ATS Installation & Operations Manual is not covered by the warranty.

3.

Before installing the system, check that the package contents are intact and complete against the packing list. If any damage is found or any component

is missing, contact your dealer.

1.4 EI ATS Enclosure Overview

1.

Status display

2.

1¼" Inverter knockouts

3.

2½" Load knockout

4.

2½" Grid knockout

5.

1¼" Communication knockout

6.

1¼" unassigned knockout

7.

1¼" Generator knockout

8.

Heat sink

9.

200A Main Circuit breaker Access door

!

!

ATTENTION – READ FIRST

!

CAUTION –

Use tools with insulated handles. Always wear appropriate PPE.

Although the Tigo ATS comes with
mounting hardware, use the appropriate
hardware for the mounting surface.

1.1 Package Contents

2.1 Mounting & opening the ATS

1.2 Required Tools

3.1 Electrical connections overview & conductor schedule

1.3 System wiring diagram

Item

Quantity

TSS-200-US ATS

1

Mounting bracket

1

Quick Start Guide

1

M5 Security screws

2

M6 expansion screw with anchor

2

3pin wiring connector

1

6pin wiring connector

2

200A circuit breaker interlocking kit

1

Item

Use

Wire cutter/crimp tool

Wiring the ATS

Philips Screwdriver

Wire terminals/Mounting

Rubber mallet/hammer

Mounting

Drill

Mounting

Level

Mounting

2.5mm-8mm Allen keys

Cover/Security Bracket/Wire Terminals

1.

Reserve at least 12” on all sides of the ATS. Install
vertically or tilted back no more than 15 degrees.

2.

Use a level and the mounting bracket to mark the
mounting holes.

3.

Drill out mounting holes to 1.7” (45mm) depth.

4.

Place the sleeve anchor in each hole, tap with the mallet/
hammer. Place mounting bracket aligned with the anchors
exposed through the screw holes and use the mounting
screws to attach to the wall.

5.

Confirm bracket is level and screws are tight then lift ATS
on to the mounting bracket.

6.

Insert security screws into each side of the bracket,
fastening the bracket to the ATS with a 4mm Allen key.

7.

Remove the caps covering the Allen head screws on the
front cover. Using a 5mm Allen key, loosen the Allen
screws and remove the cover.

!

CAUTION

- Check that all Disconnect switches are OFF before wiring. Do not install any component of the EI System while

energized. Always wear appropriate PPE.

1

3

-

4

5

6

COM

G

EN

ERATOR

INV3

INV3

INV1

LOAD

GRID

1

2

5

6

7

3

4

8

2

2

9

Inverter
communications
terminals

Manual Bypass
Jumper

200A Main Circuit Breaker

L1

L1

L2

L2

Load terminals

Neutral terminals

Ground terminals

Inverter
terminals

Neutral
terminals

Note –

3 additional 2½” knockouts.

2 on the back. 1 on the right side.

PV

Grid

N L2 L1

Utility
Meter

N

G

Main Panel

Load

L2 L1

Grid

L2 L1

N

G

Grid

G

Inverter

L1 L2

N

G

PV1+ PV1-

PV4+ PV4-

G

N

200A

Breaker

Breaker

Battery

BAT+ BAT-

ATS

EI Inverter

Refer to inverter manualfor

parallel dualbatteries

PV array

Generator

L1 L2

N

G

Future

enhancement

Backup

+ -

≥12”

≥12”

≥12”

≥12”

≥12

≤15°

PN: 002-00094-00 | REV 5.0 | Nov. 9, 2022