Site Preparation
Dimensions and Weights
Thermo Scientific
iCAP Qnova Series ICP-MS Pre-Installation Requirements Guide (P/N BRE0006946, Revision B)
2-11
The fore vacuum pump Sogevac SV40BI must be placed on a drip pan
of sufficient volume. Order a drip pan at Thermo Fisher Scientific or
use a suitable one of your own.
If no space for the pump is available beneath the workbench, you can
place the pump near the left side of the bench. In this case, the left side
of the iCAP Qnova Series instrument ideally aligns with the left side of
the workbench.
shows the connections for the fore vacuum pump on the
left hand side of the instrument.
A stainless steel vacuum hose with a length of 2 m and an OD of 52 mm
is delivered with the instrument for the vacuum connection, see
3
in
. The flange diameter is 40 mm (Iso-KF 40). For the exhaust
connection (
4
in
), tubing of 2.7 m length with an OD of
20 mm (ID 13 mm) is delivered with the instrument.
If you need a longer vacuum hose, contact Thermo Fisher Scientific.
Because of the large bending radius of the hose, the actual reach of the
vacuum hose is shorter than the given length. Either run the vacuum
hose left of the workbench or make a cutout through the bench for it.
The cutout must have minimum dimensions of 10 cm × 10 cm. Allow
for room to run the power cord and the exhaust tubing from the fore
vacuum pump through the cutout as well.
NOTICE
Thermo Fisher Scientific recommends the use of the noise reduction
cover when installing the fore vacuum pump.
Labeled Components: 1=data connection, 2=grounding bolt, 3=fore vacuum
connection, 4=interface pump (fore vacuum pump) exhaust connection
Figure 2-10.
Connections for fore vacuum pump
3
1
4
2
Содержание iCAP Qnova Series
Страница 1: ...iCAP Qnova Series ICP MS Pre Installation Requirements Guide BRE0006946 Revision B April 2018 ...
Страница 2: ......
Страница 3: ...BRE0006946 Revision B April 2018 iCAP Qnova Series ICP MS Pre Installation Requirements Guide ...
Страница 92: ......
Страница 93: ......
Страница 94: ......