4.2 Assembly of the bin lift system on the body of the refuse collection vehicle
Tools required:
- Spanners/ring spanners 10, 19 and 24 mm.
- Mobile hoist/crane with minimum lifting capacity 1000 kg.
- Hoist beam with chains.
- Make sure that the refuse collection vehicle on which the bin lift is
being mounted is standing on a level surface.
- Switch off the engine of the refuse collection vehicle and remove the
ignition key from the ignition switch (keep on your person).
- Fit the supports (A) for the bin lift to rest on at the correct height at
the back of the refuse collection vehicle.
- Fit a guide plate between these supports at a minimum angle of 45°; this plate is to guide the tipped waste
into the hopper.
- Make sure that the lifting chairs are in the lowest position before beginning to lift.
- Connect the bin lift to a hoist beam.
- Raise the bin lift to build-on height using a lifting installation with minimum lifting capacity of 1000 kg.
- Position the bin lift on the assembly supports (A).
- Fix the bin lift to the assembly frame on the refuse
collection vehicle using M16 bolts (class 8.8), lock nuts and
washers (DIN 6340) with a tightening torque of 200 Nm.
* Build on height for loaded vehicle,
minimum: 1140mm
maximum: 1200mm
Terberg Machines B.V. recommends: 1200mm.
When mounting the bin lift on the compaction
body standard EN 1501-5 shall be observed.
Ensure that the support is strong enough to
bear the load of the bin lift system plus the
weight of a full bin/container (max. total weight).
420
955
145
7
189
5
0
min. 45°
141
0
153
6
A
A
11
40
- 1
20
0 m
m*
Ø18
BACK OF REFUSE
COLLECTION VEHICLE
DETAIL of support (A)