Step #7
Prepare the Cryochiller Unit for Operation
•
•
Remove the manifold
•
• Backseat the compressor’s suction and discharge service valves.
•
•
Remove the hoses.
•
Re-install the flare nuts and seals on the access fittings of the service valves on the compressor.
•
Leak check the stems of the service valves. Replace valve stem caps
•
•
If the refrigerant recharges were shipped in disposable cylinders. They are intended for one time
use only. Cylinders should be properly disposed of. These cylinders can be recycled.
•
If the gas charge was shipped in reusable cylinder these can be used for future gas recovery. Non-
contaminated recovered gas can be save and used as “top off gas”.
•
System is ready to run. Please note the psi of the unit before starting the compressor, for future
reference to confirm if system has a leak. Pressure should be taken with CT reading approximatly
20C.
Содержание Cryogenics
Страница 12: ...Discharge valve Bitzer Comp Suction valve Bitzer Comp Suction valve Emerson Comp Discharge valve Emerson Comp...
Страница 17: ......
Страница 20: ...Charging with disposable tank using recovery pump...
Страница 21: ...Charging with refillable tank using recovery pump...
Страница 24: ...Charging using compressor on suction side of compressor...