10 

 

9.2 

Maximum working performance: 

The maximum working performance is represented by the possibility of bending together one or more 
bars, according to the diameter and strength of the rod. 
Mandrels indicated in the following tables show maximum performances of the machine not keeping in 
consideration the iron yield point. For constructions made in reinforced concrete it is necessary to use 
the mandrels complying with Laws in force. 

 

Type 

PG 26  three-phase

 

PG 30  three-phase

 

n°bars 

Ø mandrel 

100 

69 

69 

55 

48 

130 

100 

69 

55 

48 

650 N/mm² 

22 

16 

14 

12 

10 

26 

18 

14 

12 

10 

850 N/mm² 

20 

14 

12 

10 

10 

22 

16 

12 

10 

10 

 

Type 

PG 35  three-phase

 

PG 40  three-phase

 

n°bars 

Ø mandrel 

130 

100 

69 

55 

48 

130 

130 

87 

68 

68 

650 N/mm² 

30 

22 

18 

14 

10 

34 

24 

18 

16 

14 

850 N/mm² 

26 

20 

16 

14 

10 

30 

22 

16 

14 

12 

 

Type 

PGT 32/25  three-phase 

Bending

 

PGT 32/25

  

three-phase 

Cutting

 

n°bars 

Ø mandrel 

130 

100 

69 

36 

36 

 

 

 

 

 

650 N/mm² 

26 

18 

14 

12 

10 

22 

16 

12 

10 

10 

850 N/mm² 

22 

16 

12 

10 

10 

20 

14 

10 

10 

10 

 

Maximum working performance for mono-phase machines: 

The supply value (VOLT) must be checked during the working process. 
 

Machine type 

Operation  

Maximum 

performance at 

220V 

Maximum 

performance at 

200V 

Maximum 

performance at 

190V 

PG 26 

– 8 turns 

Bending 

Ø22 (mandr. Ø100) 

Ø20 

Ø18 

PG 26 

– 12 turns 

Bending 

Ø18 (mandr. Ø100) 

Ø16 

Ø14 

PG 30 

Bending 

Ø24 

Ø22 

Ø20 

PGT 32/25 

Bending 

Ø24 

Ø22 

Ø20 

PGT 32/25 

Cutting 

Ø20 

Ø18 

Ø16 

 
Supply cable for mono-phase machines:

 

An inappropriate supply cable can cause a voltage drop decreasing the machine performance. 

Supply cable section: 

2,5 mm² for a cable with maximum length 15 meters 
4 mm² for a cable with maximum length 60 meters 
6 mm² for a cable with maximum length 80 meters 
 

 
 
 

Содержание PG 26 mono-phase 2 speed

Страница 1: ...30 three phase PG 30 mono phase PG 35 three phase PG 40 three phase Via Giovanni Quarena 225 B 25085 GAVARDO BS ITALY Tel 0365 31428 34141 34221 Fax 0365 373030 www tecmor it E MAIL info tecmor it PGT 32 25 three phase PGT 32 25 mono phase Speed variator 9x9 Panel Combined machines Bending machines ...

Страница 2: ......

Страница 3: ...eakdown 11 11 Maintenance inspections and checks 11 12 Cleaning 12 13 Machine keeping 12 14 Demolition and disposal 12 15 Safety instructions 12 16 Safety devices 12 17 One man safety devices 13 18 Residual risks 13 19 Instructions for warranty assistance 13 20 Spare parts 13 ENCLOSURES ELECTRICAL DRAWING WARRANTY CERTIFICATE IMPORTANT Send us the WARRANTY CERTIFICATE enclosed to the present handb...

Страница 4: ... own responsibility that the following product MACHINE TYPE PG 40 SERIAL N 1503126 YEAR OF CONSTRUCTION 2015 To which this declaration is referred complies with the following regulations Legislation 06 42 CE 06 95 CE 04 108 CE Regulations UNI EN ISO 12100 CEI EN 60204 1 70 1 44 5 D L G S 81 08 Gavardo Italy 31 03 15 administrator Mora Gaetano 2 ...

Страница 5: ...83 330 100x85xh88 PGT 32 25 Three phase 10 1 1 275 80x88xh86 PGT 32 25 Mono phase 10 1 5 275 80x88xh86 1 4 Marking The Certificate of Conformity on page 2 shows the following information Name and address of the producer CE mark Type of machine Serial number Year of construction The same data are indicated on a plate fixed on the machine 2 Transport and unpacking The machine is delivered on a palle...

Страница 6: ...assage ways and avoiding mechanical efforts and damages The machine is equipped with a movable socket to be connected with the supply cable it will be inserted into the fix plug in the machine system 4 4 It is compulsory to connect the machine with a grounding system with a resistance value able to grant a contact tension not higher than 25V For a better grounding there is the possibility to conne...

Страница 7: ...by the picture the position reserved to the worker is in the front of the machine which is indicated by the machine plate 8 Use of the machine 8a Use of the standard machine 8a 1 General controls of the machine 1 Protection for the bending area 2 Regulation handle 3 Emergency STOP button 4 Supply light 5 Return reset button 6 Remote control for pedal used by operator 7 Speed selector only PG 26 mo...

Страница 8: ... gets into the starting position ready for the following operations 8a 3 How to bend a piece After all the above described operations prepare the toolings as follows a Bending operation with square The picture shows the correct position of the equipment ready for the bars bending using the square only for iron with maximum diameter 14 mm The bending square allows to place the bar near the bending ...

Страница 9: ... the starting position 0 into position 1 or 2 Insert a pin at 180 from the point 0 Push the reset button now the light is on When the machine is stopped and the disc is in the starting position le blades are completely open Insert the bars to be bent into the space between the blades under the shear protection and put them at the required length Execute the cutting operation through the remotely c...

Страница 10: ...The reset operation has to be executed each time that The machine stops because of the emergency stop button Voltage is untimely restored A starting operation is executed through the main inverter switch To start the machine after an emergency STOP it is necessary to unblock the button turning its mushroom part and then to push the reset button in this way the disc gets into the starting position ...

Страница 11: ...ected on 0 e Push the button for programme activation deactivation the light is off and the programme is not active f Keep the RESET button pressed for 4 5 sec and start the programme with the 1 bending Bending repetition a Push the button for programme activation deactivation light on b Using the bending buttons select the required bending c Push the button for programme activation deactivation l...

Страница 12: ...18 14 10 34 24 18 16 14 850 N mm 26 20 16 14 10 30 22 16 14 12 Type PGT 32 25 three phase Bending PGT 32 25 three phase Cutting n bars 1 2 3 4 5 1 2 3 4 5 Ø mandrel 130 100 69 36 36 650 N mm 26 18 14 12 10 22 16 12 10 10 850 N mm 22 16 12 10 10 20 14 10 10 10 Maximum working performance for mono phase machines The supply value VOLT must be checked during the working process Machine type Operation ...

Страница 13: ...submit periodically the following checking 11 1 Oil level Monthly check the oil level and add it in case the level is too low The complete oil substitution is recommended each 4 000 working hours unloading all the spent oil in the reducer unscrewing the unload cap After the unload cap cleaning screw it and full the reducer pouring the oil through the load cap in the quantity required by the indica...

Страница 14: ...t be removed or modified c Dimensions and shapes to be bent or cut cannot be foreseen and for this reason the worker must produce some supports if necessary to avoid any danger for the worker himself 16 Safety devices The machine is provided with the following safety devices 16 1 Magneto thermic switch and differential 16 2 Grounding of the machine body 16 3 Button for emergency stop The machine i...

Страница 15: ...ate of delivery and the guarantee is valid only if the GUARANTEE CERTIFICATE sheet enclosed has been duly filled in and sent to TECMOR company OTHERWISE THE MACHINE WILL NOT BE COVERED BY GUARANTEE 2 The producer undertakes to repair any manufacturing defect found during the period of guarantee That means the free replacement of the faulty parts after the producer has made sure of the manufacturin...