Fusion Wideband Installation Procedures
7-12
InterReach Fusion Wideband Installation, Operation, and Reference Manual
CONFIDENTIAL
D-620616-0-20 Rev F
Figure 7-1
Flush Mounting Bracket Detail
Consideration:
• The Fusion Wideband Main Hub is shipped with #10-32 mounting screws.
Another common rack thread is #12-24. Confirm that the mounting screws match
the rack’s threads.
To install the Hub in a rack:
1.
Insert spring nuts into rack where needed or use existing threaded holes.
2.
Place the Hub into the rack from the front.
3.
Align the flange holes with the spring nuts installed in Step 1.
4.
Insert the mounting screws in the appropriate positions in the rack.
5.
Tighten the mounting screws.
Installing an Optional Cable Manager in the Rack
• Using the screws provided, fasten the cable manager to the rack, immediately
above or below the Main Hub.
Installing a Main Hub Using the 12” Wall-Mounted Rack (PN 4712)
Considerations:
Содержание InterReach Fusion ADCP-77-044
Страница 12: ...CONFIDENTIAL 4 InterReach Fusion Wideband Installation Operation and Reference Manual D 620616 0 20 Rev F...
Страница 16: ...CONFIDENTIAL 4 InterReach Fusion Wideband Installation Operation and Reference Manual D 620616 0 20 Rev F...
Страница 203: ...Help Hot Line U S only 1 800 530 9960 A 3 D 620616 0 20 Rev F CONFIDENTIAL Figure A 2 CommScope 2279V for RG 6...
Страница 210: ...A 10 InterReach Fusion Wideband Installation Operation and Reference Manual CONFIDENTIAL D 620616 0 20 Rev F...
Страница 216: ...B 6 InterReach Fusion Wideband Installation Operation and Reference Manual CONFIDENTIAL D 620616 0 20 Rev F...