Commissioning
The system operator is responsible for the correct operation of the fan and/or the system!
Warranty claims can only be made if commissioning work is carried out correctly and written evidence thereof is
provided.
It is recommended to fill out the commissioning report 18
12.1 Safety information
♦
Commissioning may only be carried out by adequately qualified persons, details see Table 1
♦
Pay attention to the safety data sheet of the chemical substances transported with the fan.
Warning
♦
Comply with fundamental information in the commissioning of the EX fan:
• DGVU 113-001 (explosion protection rules (EX-RL))
• TRGS 727 (Avoiding ignition hazards due to electrostatic charges).
• Observe and respect local conditions, regulations and laws.
12.2 Preconditions
♦
Installation and electrical connection have been
correctly performed.
♦
Residual material from installation and foreign objects
have been removed from the fan and ducts.
♦
Inlet and outlet are free.
♦
Safety devices have been fitted.
♦
Ground cable is connected.
♦
Cable glands are tight.
♦
Data on the name plate corresponds with the
connection data.
♦
For EX fans, check whether the minimum air gap
between the rotor and the housing matches the value
stated in 6.6
12.3 Tests
♦
Before switching the fan on, check for externally visible damage and ensure that the protective equipment functions
properly.
1. Switch the fan on.
2. Do the tests requested in the commissioning report (18
Speed controllable fans: “Measured data at commissioning” at maximum speed
3. Switch the fan off.
| 008