Installation with the ALV
1. Cut an opening in the wall according to the dimensions
specified in the dimension table and the dimension
print. Place the ALV commissioning box in the opening.
Insert the mounting frame into the commissioning box
and secure it with screws in the short sides through
the sides of the commissioning box and into the wall
structure.
2. Insert the measurement hose and the cord for damper
adjustment through the air distribution plate in the
mounting plate and press it into the mounting frame.
The mounting frame is held in place by its spring
retainers. Mark the positions for the bore holes.
p
q
ROWb 400 -150
Tomelilla
Sweden
+ALVd 400-150-125
k-faktor
B-ansl 10,0 / K-ansl 9,9
k
p
q
⋅
=
k
p
q
=
( )
2
q
= uppmätt flöde l/s
p
= aktuellt mättryck (Pa)
k
= injusteringsfaktor
k
k-faktor
p
q
ROWb 400 -150
Tomelilla
Sweden
+ALVd 400-150-125
k-faktor
B-ansl 10,0 / K-ansl 9,9
k
p
q
⋅
=
k
p
q
=
( )
2
q
= uppmätt flöde l/s
p
= aktuellt mättryck (Pa)
k
= injusteringsfaktor
k
k-faktor
Figure 2. ROW + ALV.
3. Bore screw holes in the wall.
4. Secure the mounting plate with screws to the wall.
5. Commissioning is carried out with the wall terminal
face temporarily secured with the screws supplied. See
Commissioning.
6. Bore the screw holes in the mounting plate for the
temporary attachment using a 5.5 mm twist drill. The
measurement hose and the commissioning cord can
be removed, if necessary, by cutting them off, level
with the air distribution plate. Or they can be pushed in
behind the air distribution plate.
7. Secure the wall terminal face using steel blind rivets.
Q =Flow reading
P = Current pressure reading
K = Commissioning factor