Flexible wall
installation MF2
installation frame
Damper blade must be closed during installation!
The wall is composed of 2x2 plasterboard boards,
12,5 mm thick, installed on a steel frame construction.
The interior of the wall is filled with mineral wool. The
minimum thickness of the wall is 100 mm.
* Create an opening according to the dimension of the
fire damper and build the subframe according to the
drawing.
1. Place the fire damper in the opening.
Damper blade must be closed during installation!
2. Fasten the fire damper with screws. (12 pcs, 6x160
mm)
Ensure that the damper is sufficiently supported.
Test the operation of the damper blade!