Installation of this type of equipment requires at least three people, and the use of a 

lifting tower or platform.

1.  Read all instructions carefully before starting assembly.

2.  Check using the parts list and fixing kit list that none of the components are missing. If  

 

any parts are missing contact our office.

3.  Plan the final position of the play equipment ensuring there is sufficient space. See   

 

ground plan for recommended safety surface area and critical fall height to EN-1176.

4.  Excavate the foundation holes in accordance with the ground plan. Orchard is  

 

 

designed to be installed onto a level site.

5.  Fit the ground shoes OPA001/006 (for wet pour surfacing) / OPA002/007 (for loose fill) to  

 

the bottom of all posts but OTP214 / 220 / 221, using 3 x coach screws (M10 x 80).  

 

Each post is numbered, and are marked with an 'X' on the bottom end.

6.  Fit the rubber post caps to the top of each post using 3 x 50mm wood screws per cap.

7.  Erect the main posts into the foundation holes using the ground plan for dimensions.  

 

Assembling decks and activities between the posts will help to brace it before it is    

 

concreted.

8.  Ensure ropes and nets are taught before concreting the posts.

9.  Assemble all activities and nets onto the posts in accordance with the assembly    

 

instructions in this document. Do not concrete the main legs until all the nets, panels,  

 

and other activities are fitted, as adjustments may be required.  

10.  Fit the two spragging irons provided through the holes in the end of the painted slide bar.

11.  When all the activities are fitted and decks are levelled, fill the foundation holes to the  

 

required depth with concrete.

12. Do not allow the equipment to be used until the concrete has set (2-3 days) and the

 

required safety surface has been installed.

13. Check that all fixing bolts are fully tightened.

14. When all fixings are secure, fill the 40mm diameter counterbores in the posts with the  

 

rubber bungs supplied.

15. Follow the maintenance instructions supplied.

NB:

 During installation, care must be taken to prevent hazards to children. If you are at all 

unsure or have any questions, please contact the contracts department immediately for their 

assistance and advice. Extra care should be taken if conditions are abnormal.

Tools Required

M10 Security screw torx fixing tool

Sockets for M16 bolts

Sockets for M10 bolts

Digging Implements

OTU/OTW210

Orchard Unit

Installation Instructions

Page 2

Rev 03

Содержание Orchard Oak

Страница 1: ...Orchard Oak OTU OTW210 Installation Instructions Page 1 Rev 03...

Страница 2: ...ed 8 Ensure ropes and nets are taught before concreting the posts 9 Assemble all activities and nets onto the posts in accordance with the assembly instructions in this document Do not concrete the ma...

Страница 3: ...es 12 NB surplus fixings are included in the kit to account for breakages and losses OTU210F Fixing Kit List CHN005 Chain Adapter 14 CZS009BK Nylon Bracket Cover 14 2 DZS005 Nylon Nut Cover 86 9 DZS00...

Страница 4: ...SL003 Page 4 Rev 03 0 10 20 30 40 50 60 70 80 90 100 110mm CHN005 OTU OTW210 Orchard Unit Fixing Kit Illustrations Not To Scale CZS009BK DZS005 DZS007 DZS009 ORS001 ORS002 ORS005 PZS001 CZS220 ORS017Z...

Страница 5: ...Page 5 Rev 03 OTU OTW210 Orchard Unit Parts List ORS003 DZA106 OPA001 006 or OPA002 007 Wet Pour or Loose Fill PED005 ORR215 ORR200 ORR210...

Страница 6: ...Page 6 Rev 03 ORA202 ORM010 ORM008 ORM003 ORM007 OTU OTW210 Orchard Unit Parts List ORM005 ORM011 DZA652 ORM001...

Страница 7: ...Page 7 Rev 03 OTU OTW210 Orchard Unit Parts List ORA206 ORM014 ORM015 PNS001 ORM009...

Страница 8: ...Page 8 Rev 03 OTU OTW210 Orchard Unit Parts List ORP004 ORP007 ORP006 ORP005 ORP001 ORP002 ORP009...

Страница 9: ...OTU OTW210 Orchard Unit Page 9 Rev 03...

Страница 10: ...OTU OTW210 Orchard Unit Page 10 Rev 03...

Страница 11: ...OTU OTW210 Orchard Unit Fixing Details Post Caps and Shoes Page 11 Rev 03 OTP223 TO BE INSERTED INTO THE GROUND FIXING BY 750mm See next page for details...

Страница 12: ...OTU OTW210 Orchard Unit Fixing Details Shoes Page 12 Rev 03...

Страница 13: ...OTU OTW210 Orchard Unit Fixing Details Post Joints and Ropes Page 13 Rev 03...

Страница 14: ...OTU OTW210 Orchard Unit Fixing Details Decks Page 14 Rev 03...

Страница 15: ...Ramp Page 15 Rev 03 WSR040 HSS550 ORS002 LKN320 WSR040 LKN320 DZS009 DZS005 MCS340 M10 x 55 Countersink Bolt MCS375 M10 x 130 Countersink Bolt This spragging iron MSL003 should feed through pre drille...

Страница 16: ...OTU OTW210 Orchard Unit Fixing details for the following activities please check coach screw length Page 16 Rev 03...

Страница 17: ...OTU OTW210 Orchard Unit Fixing details for the following activities please check coach screw length Page 17 Rev 03...

Страница 18: ...OTU OTW210 Orchard Unit Fixing details for the following activities please check coach screw length Page 18 Rev 03...

Страница 19: ...OTU OTW210 Orchard Unit Fixing Details Panel Fixing Page 19 Rev 03 This assembly of fixings also features on the larger leaf panels and framework...

Страница 20: ...OTU OTW210 Orchard Unit Fixing Details Slide Bars Climbing Wall Page 20 Rev 03...

Страница 21: ...OTU OTW210 Orchard Unit Fixing Details Climbing Wall Grips Page 21 Rev 03 Grips on the climbing wall should be positioned in the pre drilled holes as illustrated...

Страница 22: ...lace if required Check loose fill safety surfaces remove any foreign elements rake level and top up if required Disposal Instructions All components should be broken down into categories of 1 Mild Ste...