Installation
Adjustment system - Installation Instructions
Page 34
6.3.5
Overall Installation
Figure 21 Connections of the electrical controller
Connect the plug of the manual switch to the electrical controller using the appropriate input
(Figure 21 Terminal No. 5)
Connect the plug of the lifting elements with electrical controller (Figure 21 Terminal No. 1-4)
Connect the power cord to the appropriate input of the electrical controller(Figure 21
Terminal No. 6)
IMPORTANT
The SUSPA Movotec SMS system can be supplied in different variants. The
supply variants contain 1 to 8 lifting elements. There is a different controller variant depending on
the supply variant. The correct variant of the controller can be supplied only if you specify the
supply variant at the time of placing the order.
If more than four lifting elements are used in a Height Adjustment System, then the two electrical
controllers must be connected to the connector contacts with a link cable (Figure 21: Connection
no. 8). There is no contact made with connection no. 7 and thus, it remains open.
CAUTION
Two controllers are necessary if you are using more than four lifting elements in
one Height Adjustment System. The power connector of the two controllers must be joined via a
connector strip or via a distribution system provided by the customer. After the power connectors
have been connected, they must be coupled to the power source (Socket).
Never connect the two controller power connectors separately to the power supply (Socket).