Self-grounding 

Hardware System  

 

 

 

 

 

8

 of 

10

 

 

 

 

 

 

 

 

 

Clamp Installation 

– Landscape Orientation 

 
 
 
 
 
 
 
 
 
 
 
 
 
 

Landscape End Clamp Installation 
 
 
 
 
 
 
 
 
 
 
 
Mid Clamp Installation 
 
 
 
 
 
 
 
 
 
 
 

End Clamps are used at the ends of a row of PV 
panels.   

Insert the T-Bolt in the Rail slot and turn 
clockwise 90° to engage the head into the slot. 
Insert Grounding T-Bolt Holder to lock T-Bolt in 
place.  

Thread the 1/4” Collar Bolt onto the top of the T-
Bolt as shown.  After positioning the End Clamp 
firmly against the PV panel frame, 

using a 7/16” 

socket, tighten to 7.5 ft. lbs. 

 

 

Insert the T-Bolt in the Rail slot and turn 
clockwise 90° to engage the head into the slot. 
Insert Grounding T-Bolt Holder to lock T-Bolt in 
place. 

Thread the 1/4” Collar Bolt onto the top of the T-
Bolt as shown.  After positioning the Mid Clamp 
firmly against the PV panel frame, 

using a 7/16” 

socket, tighten to 7.5 ft. lbs. 

 

 

 

Proceed with the mounting of the PV panels 
using the mid and end clamps.  Specific 
mounting instructions are shown in the following 
sections for Portrait and Landscape mounting. 

Installing Mid Clamps:  A mid clamp is used 
between PV panels. It will produce 1/2” spacing 
between PV panel frames. 

An End Clamp is used to secure PV panels at 
the ends of a row. 

 

Содержание UL2703

Страница 1: ...Self grounding Hardware System 1 of 10 Self grounding Hardware UL2703 Compliant Pub D10010 V001 Copyright 2016...

Страница 2: ...A The self grounding and bonding system is for use with PV modules that have a maximum series fuse rating of less than 15A TABLE OF CONTENTS Installer Responsibility 3 Safety 3 SunModo Self grounding...

Страница 3: ...odes including periodic re inspection of the installation for loose components loose fasteners and any corrosion such that if found the affected components are to be immediately replaced Installer to...

Страница 4: ...rough all of the SunBeam racking components including the Pipe Caps I Beams Posts and Post Base Plates All hardware meet UL2703 Grounding and Fire Standards The basis of the system is our patented sta...

Страница 5: ...Clamp Kit with adaptor for standard rail and integral grounding fits panel height from 31 to 50 mm For last 3 digits see table on last page May be repositioned until torqued to final value K10183 XXX...

Страница 6: ...e screw threads and a torque wrench be used to measure the bolt torque during final assembly Hardware Torque lbs 1 4 20 Bolts and Hex Flange Nut 7 5 ft lbs 1 4 20 Ground Lug Flange Nut with 7 16 Hex H...

Страница 7: ...on shown insert the T Bolt into a T Bolt Holder for grounding the panel to the Rails Insert the T Bolt in the Rail slot and turn clockwise 90 to engage the head into the slot Insert Grounding T Bolt H...

Страница 8: ...ighten to 7 5 ft lbs Insert the T Bolt in the Rail slot and turn clockwise 90 to engage the head into the slot Insert Grounding T Bolt Holder to lock T Bolt in place Thread the 1 4 Collar Bolt onto th...

Страница 9: ...NEC 690 43 Each Rail should have a Ground Lug for fastening the ground conductor to the array The Ground Lug is mounted on the top or side of the Rail using a special 1 4 T Bolt Grounding Spacer and...

Страница 10: ...015 002 Clamps Part End Part Mid Size T Bolt in T Bolt PN Landscape K10183 031 K10182 157 31 mm 1 57 B20015 013 Landscape K10183 033 K10182 157 33 mm 1 57 B20015 013 Landscape K10183 040 K10182 157 40...

Отзывы: