Fig. 5-1
Hoisting the MV Station
5.2.2 Hoisting
During the whole hoisting process, please observe the following rules:
Hoist the MV Station in a vertical manner. Do not drag or drop the MV Station on any
surface.
When the MV Station has been hoisted for about 300mm away from the ground, stop
to check if all the connections are still firm. After confirmation, continue hoisting the MV
Station.
When transported to the final location, the MV Station should be put down slowly and
steadily.
The final location should be firm, level, and well-drained. The MV Station is supported
by four bottom fittings on the ground.
The MV Station should be hoisted by four top corner fittings as shown in the following figure.