Commissioning
6.1
Inspection before Commissioning
No.
Inspection item
Result
1
All cables are intact, well-insulated, and appropriately
dimensioned
□
2
All cables are connected correctly and firmly
□
3
The polarity of the power supply cable is correct. The
grounding cable is reliably grounded
□
6.2
Commissioning Steps
No.
Step
Result
1
Inspection before commissioning
□
2
Power on the Logger1000.
□
3
Check whether the indicators of Logger1000 normally flash.
□
4
Connect the debugging PC to the "ETH" port of the Logger1000
via the network cable (default IP address of "ETH":
12.12.12.12).
Log in the Web at 12.12.12.12 through the IE, Safari or Chrome
browser.
□
5
Make sure the communication cable connecting the device and
the Logger1000 is firmly in place, and connect the DC circuit
breaker of the inverter to ensure the inverter is supplied with
power.
□
6
Set serial port parameters by referring to the
chapter, including the baud rate, check bit, data bit, and
stop bit.
The default setting is 9600bps, 8 data bit, 2 stop bit, and no
check bit.
□
Содержание Logger1000
Страница 2: ......
Страница 6: ......
Страница 10: ......
Страница 28: ...18 step 3 The installation of the power box and Logger1000 is completed End 4 Mechanical Mounting User Manual...
Страница 94: ...M H 001405 www sungrowpower com Sungrow Power Supply Co Ltd...