Sun Storage 2500-M2 Arrays
Site Preparation Guide
Part No.: E20737-02August 2011
Страница 1: ...Sun Storage 2500 M2 Arrays Site Preparation Guide Part No E20737 02 August 2011 ...
Страница 2: ...iel et la documentation qui l accompagne sont protégés par les lois sur la propriété intellectuelle Ils sont concédés sous licence et soumis à des restrictions d utilisation et de divulgation Sauf disposition de votre contrat de licence ou de la loi vous ne pouvez pas copier reproduire traduire diffuser modifier breveter transmettre distribuer exposer exécuter publier ou afficher le logiciel même ...
Страница 3: ... Secure Installation Requirements 2 Placement of a Product 2 2 Sun Storage 2500 M2 Arrays Specifications 5 Dimension and Weight Specifications 6 Environmental Requirements 7 Humidity 7 Altitude 8 Airflow and Heat Dissipation 8 Acoustic Noise 9 Shock and Vibration 9 Electrical Requirements 9 Site Wiring and Power 10 AC Power Input 11 ...
Страница 4: ...eparation Guide August 2011 DC Power Input 11 Controller Tray Power Factor Correction 11 Power Cords and Receptacles 11 AC Power Cords 11 DC Power Connector Cables 12 Battery Life 12 A Configuration Worksheets 13 ...
Страница 5: ... helps you make decisions about ventilation electrical power floor loading and network configuration Conduct a power survey to make sure that the storage array and input power is free of noise spikes and fluctuations Before You Read This Guide Before you begin to install Sun Storage 2500 M2 Arrays you must have already read the regulatory and safety requirements described in this book Sun Storage ...
Страница 6: ...s Sun Storage Common Array Manager Release Notes Prepare the site Sun Storage 2500 M2 Arrays Site Preparation Guide Install the array Sun Storage 2500 M2 Arrays Hardware Installation Guide Install the management software Sun Storage Common Array Manager Quick Start Guide Sun Storage Common Array Manager Installation and Setup Guide Install multipath driver Sun StorageTek MPIO Device Specific Modul...
Страница 7: ...s concerning facilities The customer is also required to do the following Comply with all local national and international codes covered in this specification The subjects covered include fire and safety building and electrical codes Document and inform Oracle Corporation of any deviations from this specification Safety Information Install Sun Storage 2500 M2 Arrays in accordance with the local sa...
Страница 8: ...or Move the cabinet slowly and deliberately and make sure that the floor is free from foreign objects and cables that the cabinet could roll over Caution To avoid injury wear protective footwear when moving a system Secure Installation Requirements To minimize personnel injury in the event of a seismic occurrence you must securely fasten the cabinet to a rigid structure extending from the floor to...
Страница 9: ...ter Failure to follow these guidelines can cause overheating and affect the reliability of your product Air cools the system cabinets from front to back Air enters at the front circulates and is expelled at the back of the cabinet The front and back door clearances provide sufficient space for cooling See Chapter 2 for specific clearance specifications ...
Страница 10: ...4 Site Preparation Guide August 2011 ...
Страница 11: ... chapter describes the physical environmental and electrical requirements for the Sun Storage 2500 M2 Arrays It contains the following sections Dimension and Weight Specifications on page 6 Environmental Requirements on page 7 Electrical Requirements on page 9 ...
Страница 12: ...ents installed Because drive weights can vary this value can vary from the value specified as much as either 0 66 lb 0 3 kg times the maximum number of drives per controller tray for 3 5 in SATA drives or 0 18 lb 0 08 kg times the maximum number of drives per controller tray for 2 5 in SATA drives Weight Empty Empty weight indicates a controller tray with the controller modules the power fan modul...
Страница 13: ...eet to 9842 feet 1000 meters to 3000 meters above sea level lower the environmental temperature 3 3 F 1 7 C for every 3280 feet 1000 meters above sea level Parameter Requirement Operating range both cabinet and subsystem 50 F to 104 F 10 C to 40 C Maximum rate of change 50 F 10 C per hour Storage range 14 F to 122 F 10 C to 50 C Maximum rate of change 59 F 15 C per hour Transit change 40 F to 140 ...
Страница 14: ... ft 30 5 m below sea level to 9840 ft 3000 m above sea level Storage 100 ft 30 5 m below sea level to 9840 ft 3000 m above sea level Transit 100 ft 30 5 m below sea level to 40 000 ft 12 000 m above sea level TABLE 2 7 Airflow and Minimum Clearance Position Clearance Front 30 in 76 cm Back 24 in 61 cm TABLE 2 8 Power and Heat Dissipation for the Controller Tray Component KVA Watts AC Btu Hr Contro...
Страница 15: ...ies meet standard voltage requirements for both North American USA and Canada operation and worldwide except USA and Canada operation They use standard industrial wiring with line to neutral or line to line power connections TABLE 2 9 Acoustic Noise at 25 C for the Controller Tray Measurement Level Sound power standby operation 6 2 bels maximum Sound pressure normal operation 6 2 bels maximum TABL...
Страница 16: ...its and associated circuit breakers must provide sufficient power and overload protection To prevent possible damage to the array isolate its power source from large switching loads such as air conditioning motors elevator motors and factory loads Power interruptions The controller tray can withstand the following applied voltage interruptions with or without an integrated uninterruptible power su...
Страница 17: ...rection Power factor correction is applied within the power supply which maintains the power factor of the controller tray at greater than 0 95 with nominal input voltage Power Cords and Receptacles Sun Storage 2500 M2 Arrays are shipped with either two AC power cords or two DC power cords per tray depending on the configuration ordered AC Power Cords Each AC power cord connects one of the power s...
Страница 18: ...connected by removing all power connectors from the power supplies Two optionally four DC power connector cables are provided with each controller or expansion tray Two DC power connectors are on the back of each tray s DC power supply if additional redundancy is required Note It is not mandatory that the second DC power connection on the array s DC power supplies be connected The second DC power ...
Страница 19: ...he information you need to collect to configure the array TABLE A 1 Sun Storage 2500 M2 Arrays Configuration Worksheet Controller A MAC address Controller B MAC address Controller A IP address Controller B IP address Management host IP address Network mask Name server domain name IP address of the domain name server DNS Gateway IP address Email notification address ...
Страница 20: ...rmation you need to collect for each data host connected to Sun Storage 2500 M2 Arrays TABLE A 2 Sun Storage 2500 M2 Arrays Data Host Information Host name Vendor Model Operating system Patch Service pack Number of HBAs HBA World Wide Name WWN HBA model HBA driver ...