STULZUltraSonic-SystemforDirectRoomHumidificationBNB-
Maintenance
11.1. Maintenance cycles
Content of general maintenance checks:
Job to be performed
Scope of checks
Time interval
1)
Page
Plant operator
Check for secure
connections
- Tightness of connections of water-bearing parts
-Cleannessoffilter
- Water tank and outside of unit for impurities
- Humidity sensor and ventilation slots for impurities
3 months
Mist guide tubes
Check mist guide tube for deposits.
3 months
Clean the water tank
Remove housing cover and retaining plate together with
mistflowpipes(openwatertank),cleananddisinfect
with hydrogen peroxide solution.
6 months
Cleantheairfilter
Openfiltercase,cleanfilter.
6 months
Leak test
Check all screw and push-in connections for leaks
- Threaded joints are secure
- Connectors are secure
6 months
Transducers
Check transducers for deposits.
6 months
Specialist engineer
Inspect electrical system
Remove cover of control system and check electrics.
6 months
Replace nebulizer print
plates
---
Approx. every 10,000
operating hours
Replace ultrasonic
humidifier
---
In the event of prob-
lems or failure
Replacefloat
switch for
supply pipe
---
Approx. every 10,000
operating hours
Replacefloat
switch for
lower water level
---
In the event of prob-
lems or failure, every
10,000 operating
hours at the latest
Replace relay PCBs
---
In the event of prob-
lems or failure
Replace fan
---
In the event of prob-
lems or failure
1)
Time intervals may be shorter in isolated cases, depending on local conditions.
1)
Visual inspections must be performed regularly!
CAUTION
Time intervals of maintenance cycles.
The time intervals of maintenance cycles may have to be adapted to suit local conditions.
NOTICE