Mounting instructions for seesaw „libra 2“ 

Item No. 512511401

Diagram 2: Side view with dimension details „libra2“

800

500

950

Füllmaterial

Filling

Beton

Concrete

Erde

Ground

0084-00-00

Fundamentplan

libra2

Rev.:

Projekt:

BESTELL-NR:

ZG-NR:

BENENNUNG:

OHNE SCHRIFTLICHE ZUSTIMMUNG DER C KAISER GMBH DARF DIESE TECHNISCHE UNTERLAGE WEDER VERVIELFÄLTIGT 

NOCH DRITTEN MITGETEILT ODER ZUGÄNGLICH GEMACHT WERDEN NOCH IN SONSTIGER WEISE MISSBRÄEUCHLICH VERWENDET 

WERDEN. ZUWIDERHANDLUNGEN WERDEN URHEBERRECHTLICH VERFOLGT.

FREIG:

GEPR:

GEZ:

DATUM:

NAME:

 

WERKSTOFF



MAßSTAB:

OBERFLAECHEN NACH

DIN ISO 1302 REIHE 2

ZUL. ABWEICHUNG

DIN 2768 - mH

+0,3

-0,3

WERKSTUECKKANTEN

NACH DIN 6784

Gewerbegebiet Larsheck

56271 Kleinmaischeid

Deutschland

A3

 

19.04.2016

Abmaße:

 

Fertigung:

Behnke

1x

Gewicht:

 

Play level

Floor anchor

1.  Select the play equipment location in consideration of the required safety 

area (see Diagram 3: 5500 x 2800mm). 

2.  The impact area of a playground equipment with an enforced movement is 

not allowed to overlap the impact area of other equipment.

 

Regarding to DIN 1176 - 4.2.8.2.5, impact absorbing surfaces have to be put 
under the whole impact area of every equipment with an enforced movement.

3.  Carry out excavation work for the foundation anchor as shown in Diagram 2. 

After excavation, compress the foundation floor.

 

Note: 

The seesaw is built in on the play level. Pay attention to items marked 

„game level“ of play equipment! 

4.  Set up the concrete foundation acc. to the dimensions indicated (LxWxH 800 

x 800 x 500 mm) with central, horizontal reinforcement (BST 500 S) in the 
quality class B 25. Make sure that the foundation anchor included in the deli-
very is cast into the foundation in such a way that the upper angle frame lies 
horizontally and fl ush mount with the surface of the foundation.

5.  After a setting period of 10-14 days, depending on weather conditions and 

foundation size, clean the surface of the foundation, place the pre-mounted 
play equipment onto it and screw the base plate of the play equipment onto 
the foundation anchor.

Reinforcement plan: 

Concrete foundation with rein-

forcement
Main foundation: BSt 500S

 

Ever 4 stirrups Ø 8 mm lengthwise and cross

 

Concrete cover h´= 3 cm
Concrete quality class B25

marking installation depth