Mounting instruction springrider „Klemens“
Item no. 51 3019 401
kleinkinder
toddlers
620
600
826
465
100
450
OHNE SCHRIFTLICHE ZUSTIMMUNG DER KAISER GMBH DARF DIESE
TECHNISCHE UNTERLAGE WEDER VERVIELFÄLTIGT, NOCH DRITTEN MITGETEILT ODER
ZUGÄNGLICH GEMACHT WERDEN, NOCH IN SONSTIGER WEISE MISSBRÄEUCHLICH VER-
WENDET WERDEN. ZUWIDERHANDLUNGEN WERDEN URHEBERRECHTLICH VERFOLGT.
1
Klemens
Benennung
Gepr.
Blatt
Datum
Projekt
Gez.
Zeichnungsnummer
1:10
A3
Name
Name
Fundamentplan
1206-00-00
Maßstab
Schramm
01.02.18
Gewerbegebiet Larsheck
56271 Kleinmaischeid
Deutschland
Beton
concrete
gewachsenes Erdreich
natural ground
Legende
stoßdämpfender Boden
shock-absorbing floor
B beliebiger Boden
24.09.20 ES
ES
22.08.18
Fundament auf 100
A
Datum
Änderung
Rev
beliebiger Boden
optional floor
Diagram 2: Foundation plan
Play level
Foundation anchor
1. Select the location of the play equipment taking into account the required
minimum space (see diagram 3).
2. Carry out excavation work for the foundation as shown in diagram 2.
After excavation compress the foundation floor.
Note:
The springrider is installed at play level.
3. Place the play equipment with foundation anchor as shown in diagram 2 in
the foundation hole.
4. Place the play equipment with foundation anchor into the concrete mass as
shown in diagram 2, so that the base plate is surrounded by a concrete thick-
ness of at least 50 mm both above and below.
5.
Pour the foundation floor with concrete to a height of appr. 100 mm.
6. After a setting period of 10 - 14 days, depending on weather conditions and
foundation size, cover the entire impact area with fall protection according to
the required drop height in accordance with EN 1176-1.
Critical drop height: 500mm
Recommended surface material: grass, sand, wood chip, gravel, synth. im-
pact protection.
7. Do not allow children to use the equipment before the installation has been
finished.
Reinforcement plan:
Concrete foundation with rein-
forcement
Main foundation: BSt 500S
Stirrups Ø 8 mm lengthwise and cross
Concrete cover h´= 3 cm
Concrete quality class C 20/25