Mounting instructions for multiplay equipment „ascendo 2 robinia“

Item-No. 517510601

1.  Select the play equipment location in consideration of the required safety 

area (see diagram 4: 10000mm x 8000mm).

2.  Carry out excavation work for nine foundations as shown in diagram 2 and 3. 

After excavation, compress the foundation floor.

 

Note: 

The combination equipment is built in on the play level. Pay attention 

to items marked „play level” of play equipment!

3.  Set up the 2 main concrete foundations, the smaller foundations, the slide 

foundation, the climbing bow foundation and the climbing slant foundation 
acc. to the dimensions indicated in diagram 3 with central, horizontal rein-
forcement. 

4.  After a setting period of 10 - 14 days, depending on weather conditions and 

foundation size - clean the surface of the foundations and start with the instal-
lation of the combination equipment.              

5.  Place the two towers as shown in diagram 2 and 3 at the main foundations 

and do a rough aligning. Please take care that the connections of the wobble 
bridge (shown in diagram 4) are positioned face to face. Rotate the robinia 

posts so, that there is a distance of ≤89mm between the stainless steel tube 

on the platform and the robinia post, to avoid traps. 

Note: Do not screw the base plates onto the foundations yet!

Diagram 2: Foundationplan

Reinforcement plan:

Concrete foundation with reinforcement
Main foundation: BSt 500S 
Ever 4 stirrups Ø 8 mm lengthwise and cross 
Concrete cover h´= 3 cm
Concrete quality class C 20/25-C25/30

5392

450

850

400

3371

A

A

3652

705

1511

3645

4808

4027

1750

600

600

950

275

2871

1846

2938

1750

400

1100

500

1000

500

979

950

1750

561

2063

1996

A-A

6336

5410

OHNE SCHRIFTLICHE ZUSTIMMUNG DER KAISER GMBH DARF DIESE 

TECHNISCHE UNTERLAGE WEDER VERVIELFÄLTIGT, NOCH DRITTEN MITGETEILT ODER 

ZUGÄNGLICH GEMACHT WERDEN, NOCH IN SONSTIGER WEISE MISSBRÄEUCHLICH VER- 

WENDET WERDEN. ZUWIDERHANDLUNGEN WERDEN URHEBERRECHTLICH VERFOLGT.

Oberflächen nach

DIN ISO 1302

Reihe 2

Zul. Abweichung

DIN 2768 - mH

1

 

ascendo 2A

Benennung

Gepr.

Werkstoff

Blatt

Datum

Projekt

Gez.

Zuschnitt

Zeichnungsnummer

Rev

Änderung

Datum

1:50

A3

Gewicht

Name

Name

Fundamentplan

1028-00-00

1068.7

Maßstab

Mattheis

02.05.17

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Gewerbegebiet Larsheck

56271 Kleinmaischeid

Deutschland

Beton

Concrete

Füllmaterial

Filling

Erde

Ground

Legende

5392

450

850

400

3371

A

A

3652

705

1511

3645

4808

4027

1750

600

600

950

275

2871

1846

2938

1750

400

1100

500

1000

500

979

950

1750

561

2063

1996

A-A

6336

5410

OHNE SCHRIFTLICHE ZUSTIMMUNG DER KAISER GMBH DARF DIESE 

TECHNISCHE UNTERLAGE WEDER VERVIELFÄLTIGT, NOCH DRITTEN MITGETEILT ODER 

ZUGÄNGLICH GEMACHT WERDEN, NOCH IN SONSTIGER WEISE MISSBRÄEUCHLICH VER- 

WENDET WERDEN. ZUWIDERHANDLUNGEN WERDEN URHEBERRECHTLICH VERFOLGT.

Oberflächen nach

DIN ISO 1302

Reihe 2

Zul. Abweichung

DIN 2768 - mH

1

 

ascendo 2A

Benennung

Gepr.

Werkstoff

Blatt

Datum

Projekt

Gez.

Zuschnitt

Zeichnungsnummer

Rev

Änderung

Datum

1:50

A3

Gewicht

Name

Name

Fundamentplan

1028-00-00

1068.7

Maßstab

Mattheis

02.05.17

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Gewerbegebiet Larsheck

56271 Kleinmaischeid

Deutschland

Beton

Concrete

Füllmaterial

Filling

Erde

Ground

Legende

Содержание Ascendo 2

Страница 1: ...kationen vorbehalten State 28 10 2019 p 1 Mounting instructions for multiplay equipment ascendo 2 robinia Item No 517510601 climbing bow tower wobble bridge slide climbing slant fireman s post climbing wall Diagram 1 Overall view of play equipment with description of individual elements ...

Страница 2: ...tube on the platform and the robinia post to avoid traps Note Do not screw the base plates onto the foundations yet Diagram 2 Foundationplan Reinforcement plan Concrete foundation with reinforcement Main foundation BSt 500S Ever 4 stirrups Ø 8 mm lengthwise and cross Concrete cover h 3 cm Concrete quality class C 20 25 C25 30 5392 450 850 400 3371 A A 3652 705 1511 3645 4808 4027 1750 600 600 950 ...

Страница 3: ... base plate is positioned in the center of the foundation 11 Drill holes into all foundations and screw the play equipment into the foundations with the included heavy duty dowels 12 Fill up and compress the holes between the foundation and the foundation hole with the excavation 13 Seal the foundation with the safety cover required for the height of fall indicated acc to EN 1176 1 Critical drop h...

Страница 4: ...f such corrosion occur on stainless steel parts they are fine to remove with an abrasive 240 grit Please take care when transporting and setting up the fact that the compo nents are made of stainless steel with no normal steel parts in contact R1500 R1500 R 1 5 0 0 1500 10000 2000 3000 4000 8000 OHNE SCHRIFTLICHE ZUSTIMMUNG DER CONRADI KAISER GMBH DARF DIESE TECHNISCHE UNTERLAGE WEDER VERVIELFÄLTI...

Страница 5: ... REIHE 2 ZUL ABWEICHUNG DIN 2768 mH 0 3 0 3 WERKSTUECKKANTEN NACH DIN 6784 Gewerbegebiet Larsheck 56271 Kleinmaischeid Deutschland A3 0201 00 00 29 04 2016 Abmaße Fertigung x x Gewicht 1573590 1 ascendo robinie2 Rev Projekt BESTELL NR ZG NR BENENNUNG OHNE SCHRIFTLICHE ZUSTIMMUNG DER CONRADI KAISER GMBH DARF DIESE TECHNISCHE UNTERLAGE WEDER VERVIELFÄLTIGT NOCH DRITTEN MITGETEILT ODER ZUGÄNGLICH GEM...

Страница 6: ...ent with wooden elements it cannot be ruled out that dry cracks may develop These natural changes of wood are dependent on climate con ditions as well as on the age and usage of the play equipment Longer dry periods may lead to more dry cracks This development however does not represent a quality defect Static properties of the equipment are not impaired See EN 1176 Bbl 1 2019 01 4 2 7 6 Dry crack...

Отзывы: