1.5 Hazardous environment around the product

Consider: explosion risk areas, lack of oxygen (e.g. tanks, pits), dangerous gases, extremes of 

temperature, hot surfaces, fire hazard (e.g. during welding), excessive noise, moving machinery.

1.6 The system

Consider the effect on the complete system of the work proposed. Will any proposed action (e.g. 

closing isolation valves, electrical isolation) put any other part of the system or any personnel at risk? 

Dangers might include isolation of vents or protective devices or the rendering ineffective of controls 

or alarms. Ensure isolation valves are turned on and off in a gradual way to avoid system shocks.

1.7 Pressure systems

Ensure that any pressure is isolated and safely vented to atmospheric pressure. Consider double 

isolation (double block and bleed) and the locking or labelling of closed valves. Do not assume 

that the system has depressurised even when the pressure gauge indicates zero.

1.8 Temperature

Allow time for temperature to normalise after isolation to avoid danger of burns.

If parts made from FKM have been subjected to a temperature above 250 °C (482 °F), it may have 

decomposed and formed flourine compounds, fluro hydrocarbons and fluro olefins. When subjected 

to temperatures above 500 °C (932 °F) parts made from FKM may ignite. Combustion residues are very 

corrosive and acidic, so acid-resistant gloves should be worn when handling, and calcium oxide/hydroxide 

can be used to neutralise it.

1.9 Tools and consumables

Before starting work ensure that you have suitable tools and/or consumables available. Use only 

genuine Spirax Sarco replacement parts.

1.10 Protective clothing

Consider whether you and/or others in the vicinity require any protective clothing to protect against 

the hazards of, for example, chemicals, high/low temperature, radiation, noise, falling objects, and 

dangers to eyes and face.

1.11 Permits to work

All work must be carried out or be supervised by a suitably competent person.

Installation and operating personnel should be trained in the correct use of the product according 

to the Installation and Maintenance Instructions.

Where a formal 'permit to work' system is in force it must be complied with. Where there is no such 

system, it is recommended that a responsible person should know what work is going on and, where 

necessary, arrange to have an assistant whose primary responsibility is safety.

Post 'warning notices' if necessary.

1.12 Handling

Manual handling of large and/or heavy products may present a risk of injury. Lifting, pushing, 

pulling, carrying or supporting a load by bodily force can cause injury particularly to the back. 

You are advised to assess the risks taking into account the task, the individual, the load and the 

working environment and use the appropriate handling method depending on the circumstances 

of the work being done.

Содержание AVM7

Страница 1: ...2 General product information 3 Installation 4 Commissioning 5 Operation 6 Maintenance 7 Spare parts Copyright 2019 Printed in GB 1231850 7 AVM7 Stainless Steel Thermostatic Air Vent Installation and Maintenance Instructions IM P123 23 CMGT Issue 7 ...

Страница 2: ...IM P123 23 CMGT Issue 6 2 ...

Страница 3: ...maximum operating limits of the product are lower than those of the system in which it is being fitted or if malfunction of the product could result in a dangerous overpressure or overtemperature occurrence ensure a safety device is included in the system to prevent such over limit situations iii Determine the correct installation situation and direction of fluid flow iv Spirax Sarco products are ...

Страница 4: ...s are very corrosive and acidic so acid resistant gloves should be worn when handling and calcium oxide hydroxide can be used to neutralise it 1 9 Tools and consumables Before starting work ensure that you have suitable tools and or consumables available Use only genuine Spirax Sarco replacement parts 1 10 Protective clothing Consider whether you and or others in the vicinity require any protectiv...

Страница 5: ...ctions this product is recyclable and no ecological hazard is anticipated with its disposal providing due care is taken except FKM Can be landfilled when in compliance with National and Local regulations waste code no 57502 rubber waste Germany Can be incinerated when in compliance with National and Local regulations Is insoluble in water Is soluble in aromatic hydrocarbons 1 16 Returning products...

Страница 6: ...o 88 extracted at 121 C for 1 hour ADI Free Animal Derived Ingredients for materials used manufacturing processes involved in producing the part Certification This product is available with the following certification EN 10204 3 1 material certificates pressure containing parts EN 10204 3 1 material certificates wetted parts including element fill subject to additional cost Typical Internal surfac...

Страница 7: ... 18 mm O D x 1 0 mm wall thickness tube butt weld DN15 D ISO 1127 Series 1 tube butt weld ends 13 5 mm O D x 1 6 mm wall thickness tube butt weld DN8 I 17 2 mm O D x 1 6 mm wall thickness tube butt weld DN10 I 21 3 mm O D x 1 6 mm wall thickness tube butt weld DN15 I Note On request other connection options are available at extra cost Please note that seat end spares for specially requested connec...

Страница 8: ... to the internals may occur Body design conditions PMA Maximum allowable pressure 7 bar g 170 C 101 5 psi g 338 F TMA Maximum allowable temperature 170 C 7 bar g 338 F 101 5 psi g Minimum allowable temperature 10 C 14 F PMO Maximum operating pressure for saturated steam service 7 bar g 101 5 psi g TMO Maximum operating temperature 170 C 338 F Minimum operating temperature 0 C 32 F Designed for a m...

Страница 9: ...allation in vertical lines with the flow upwards to ensure self draining operation Do not expose the element to superheat conditions since over expansion may result Suitable isolation valves must be installed to allow for safe maintenance replacement Open isolation valves slowly until normal operating conditions are achieved Check for leaks 3 5 If the trap is to be subjected to a hydraulic test at...

Страница 10: ...ine and any pressure allowed to safely normalise to atmosphere The product should then be allowed to cool When reassembling ensure that all joint faces are clean Always ensure the correct tools safety procedures and protective equipment are used at all times 6 2 How to fit new internals Remove nuts and bolts The end connection with internal seat gasket and capsule assembly can then be removed for ...

Страница 11: ... assembly 2 O ring packet of 3 3 How to order spares Always order spares by using the description given in the column headed Available spares and state the size type and end connection of the unit Example 1 Element assembly for a Spirax Sarco AVM7 stainless steel thermostatic air vent having screwed NPT connections 3 O ring 2 5 5 Fig 2 7 Spare parts ...

Страница 12: ...IM P123 23 CMGT Issue 6 12 ...

Отзывы: