0190201R1 Page 2 of 2
925 FIRST AVENUE, CHIPPEWA FALLS, WI 54729 / 800-235-1262 / 715-723-6750 / WWW.SPECTRUMFURNITURE.COM
© 2019 Spectrum Industries Inc., All rights reserved.
2. Install front stacking brackets
1.
Open the upper Connect10 door.
Figure 2
.
2.
Lift the front of the upper Connect10 slightly to install the left and right
stacking brackets. The brackets hook into the upper vent slot of the
lower locker.
3.
Secure each bracket inside the upper locker with one 1/4-20 x 15mm
JC bolt.
4.
Tighten
all
bracket screws securely.
Right stacking
bracket
3. Security anchors
The unit can be anchored to a floor, permanent worksurface, or wall for
stability and security.
Anchoring is required for stability of stacks of
2 or
more lockers.
Two #14 x 1-3/4” PHSM screws are provided with the locker for anchoring
to a wood worksurface or wall stud. Fasteners for concrete applications
are not provided. It is the customer’s responsibility to install and use
sufficient fasteners for the application.
Figure 3
.
Figure 2
Figure 3
Left stacking
bracket
Lower Connect10 Locker
Upper Connect10 Locker
1/4” hole
Wall
5/16” hole
5/16” hole
Permanent worksurface or floor