![Sonnen sonnenBatterie pro 2.0 Скачать руководство пользователя страница 13](http://html1.mh-extra.com/html/sonnen/sonnenbatterie-pro-2-0/sonnenbatterie-pro-2-0_instructions-for-use-manual_1321594013.webp)
Commissioning | 5
KD-523 | 22375 | EN | X00
13 / 16
5 Commissioning
5.1 Commissioning new systems
Proceed as follows to configure and commission a sonnenBatterie pro 2.0.
Conditions:
ü
Ordered sonnenBatterie pro 2.0 kit
ü
Received pairing code
If you have not received a pairing code, please contact your sales representative at sonnen.
1.
Establish a connection between the laptop/pc and the storage system master, as de-
scribed in the respective installation instructions.
2. Navigate to the ‘System selection’ page of the commissioning assistant 2.0
5
, as de-
scribed in the respective installation instructions. If this page does not appear:
►
Make
sure that the first page of the commissioning assistant is displayed.
3. Select the ‘sonnenBatterie pro’ button on the ‘System selection’ page.
4. Enter the activation code of the pro 2.0 and start the commissioning assistant.
5. Run the commissioning assistant until it is fully complete.
5.2 Commissioning existing systems
In the case of systems that were previously three storage systems connected in parallel,
proceed as follows:
1.
Disconnect the power supply to the storage systems (see section ‘Decommissioning’ in
the installation instructions for the relevant storage system).
2. Define which storage system will act as the master, and which as slave 1 and slave 2.
3. Carry out all necessary installation changes (see Electrical installation [P. 10]).
4. Uninstall all surplus power meters for the two slave storage systems.
5. Recommission the storage system.
6. Commission the storage system as described in section Commissioning new systems
5
Function only available in commissioning assistant 2.0!
Содержание sonnenBatterie pro 2.0
Страница 15: ......
Страница 16: ...sonnen GmbH Am Riedbach 1 D 87499 Wildpoldsried ...