Commissioning
4
4 Commissioning
To switch on the storage system, the fuse switch F1 and switch S1 must be engaged
in a specific order. F1 and S1 are located under the cover at the top side of the
storage system.
4.1.1 Removing the cover
F1
XMOD
1
2
Figure 2: Removing the cover (2) at the top side
of the storage system
►
Remove the knurled nut (1).
To do this, rotate the knurled nut (1)
counterclockwise.
►
Remove the cover (2).
4.1.2 Switching on the storage system
Figure 3: Fuse switch F1 and switch S1 at the top
side of the storage system
1 Press switch S1 and hold it down
while the following steps are carried
out.
2 Switch on fuse switch F1.
3 Keep switch S1 held down for at
least another 5 seconds.
4 Release switch S1.
The storage system then starts up and performs a self-test. Once the self-test is
successful, the storage system is ready to operate.
►
Mount the previously removed cover.