5 Commissioning 

5.1 Commissioning the storage system 

It is essential to follow the instructions in the given order when switching on the storage system with 
sonnenProtect, because otherwise the storage system cannot function properly. 

 

5.1.2 Switching on the storage system 

If the storage system cannot be switched on: 

 Do not attempt to switch on the storage system more than three 

times. 

 Contact the sonnen support Australia! 

Further attempts can damage the battery modules. 

 

Fuse switch F1 establishes the connection between the battery and the inverter.  

 

 

1 Switch on fuse switch F1. 
 

 
 
 
 
 
 

 

 

 

 
 
 
 

The storage system then starts up and performs a self-test. Once the self-test is successful, the storage system 
is ready to operate. 
 

5.1.2 Switching on the grid voltage 

 Switch on the grid voltage using the AC miniature circuit breaker. 

 

 

 

 

 

 

Содержание Protect 1300-AU-IN-ATS

Страница 1: ...Operating instructions sonnenProtect 1300 AU IN ATS KD AUD0420 Art Nr 130003 Version X01 support sonnen com au www sonnen com au...

Страница 2: ...he product environment 5 2 5 Voltage inside the sonnenProtect accessories 5 3 Product description 6 3 1 Technical data 6 3 2 System components 7 4 Function 7 4 1 Basic principle 7 4 2 Grid operation n...

Страница 3: ...the storage system and the sonnenProtect 1 2 Designations in this document The following designations are used in this document complete designation designation in this document sonnenBatterie eco 9...

Страница 4: ...f the sonnenProtect must not be connected to the building mains Only connect an electrical consumer that does not exceed the nominal power in continuous operation and maximum power when switched on of...

Страница 5: ...otect and the storage system must be wired in accordance with the product documentation The number of plug outputs on the sonnenProtect must not be changed All repairs on the sonnenProtect must be per...

Страница 6: ...ed Switchover time approx 15 seconds Safety Minimum Protection Standard IEC 61009 1 AS NZ 61009 1 Required Protective functions Overcurrent Earth Leakage required Degree of protection Specified by ins...

Страница 7: ...echnical data 4 2 Grid operation no grid outage If the public electricity grid is not experiencing an outage the backup load circuits connected to the sonnenProtect backup supply will be continuously...

Страница 8: ...switched on Do not attempt to switch on the storage system more than three times Contact the sonnen support Australia Further attempts can damage the battery modules Fuse switch F1 establishes the con...

Страница 9: ...ecking function Maintenance interval Action to be taken Every 6 months Check the function of the insulation monitor with help of the Test key see 3 2 6 2 Cleaning Risk of material damage due to use of...

Страница 10: ...system The RCD and or overall power from the sonnenBatterie is switching off immediately or after the sonnenProtect has been operating for a longer period An electrical consumer with a power consumpti...

Страница 11: ...tect Danger to life due to electrocution The sonnenProtect must only be uninstalled by authorized electricians 8 1 2 Disposal The sonnenProtect must not be disposed of as domestic waste Dispose of the...

Страница 12: ...12 www sonnen com au www sonnensupport com au...

Отзывы: