5 Commissioning
5.1 Commissioning the storage system
It is essential to follow the instructions in the given order when switching on the storage system with
sonnenProtect, because otherwise the storage system cannot function properly.
5.1.2 Switching on the storage system
If the storage system cannot be switched on:
►
Do not attempt to switch on the storage system more than three
times.
►
Contact the sonnen support Australia!
Further attempts can damage the battery modules.
Fuse switch F1 establishes the connection between the battery and the inverter.
1 Switch on fuse switch F1.
.
The storage system then starts up and performs a self-test. Once the self-test is successful, the storage system
is ready to operate.
5.1.2 Switching on the grid voltage
►
Switch on the grid voltage using the AC miniature circuit breaker.