Supported AC Grids
Figure 2: AC grids supported by SolarEdge three phase inverters
NOTE
Grid support depends on the inverter model. Some three phase inverters
support the 208V 3-wire grid. Refer to
Setting the Inverter to Support 208V 3-
Installation Procedure
The following is the procedure for installing and setting up a new SolarEdge site. Many
of these also apply to modification of an existing site.
1.
Connecting Power Optimizers in Strings
page 25.
2.
Recording power optimizer serial numbers (optional)
, page 64.
3.
4.
Connecting the strings and the AC to the Safety Switch
5.
Commissioning and activating the installation
6.
Connecting the inverter to the monitoring platform
, page 65.
Installation Equipment List
Standard tools can be used during the installation of the SolarEdge system. The
following is a recommendation of the equipment needed for installation:
Allen screwdriver for 5mm screw type for the inverter cover, Safety Switch cover,
and inverter side screws
Standard flat-head screwdrivers set
-
Three
Phase
System
Installation
Guide
MAN-01-00527-1.
2
14
Supported AC Grids