![SolarEdge SE100KUS Скачать руководство пользователя страница 44](http://html1.mh-extra.com/html/solaredge/se100kus/se100kus_installation-manual_1313727044.webp)
Chapter 5: Activating, Commissioning and
Configuring the System Using the Inverter
SetApp
If applicable, you can connect communication options at this stage, as described in
Setting Up Communication on page 61.
Once all connections are made, the system should be activated and commissioned
using the Inverter SetApp mobile application. You can download the app from the
Apple App Store and Google Play prior to reaching the site.
Internet connection is required for the download and for the one-time registration,
however not required for using the SetApp.
Step 1: Activating the Installation
During system activation, a Wi-Fi connection is created between the mobile device
and the inverter and the system firmware is upgraded.
Before activation
- download, register (first time only) and log-in to SetApp on your
mobile device. Internet connection is required for the download and for the one-time
registration. Verify that the application is updated with the latest version.
To activate the inverter:
1. Turn ON the AC circuit breaker on the main distribution panel.
2. Move the Connection Unit DC switch to the ON position.
3. Open SetApp and follow the instructions on the screen (scan the inverter bar-
code; move the ON/OFF/P switch to P position and release within 5 sec. back to
ON (1) position). SetApp creates a Wi-Fi connection, upgrades the inverter
CPU firmware and activates the inverter.
Chapter 5: Activating, Commissioning and Configuring the System Using the
Inverter SetApp
43