SOFAR 7K~10.5KTLM-G3
User manual
Copyright © Shenzhen SOFAR SOLAR Co., Ltd
- 38 -
5. Commissioning of inverter
5.1. Safety inspection before commissioning
Ensure that DC and AC voltages are within the acceptable range of the
inverter.
Attention
5.2. Start inverter
Step 1:
Turn ON the DC switch.(optional)
Step 2:
Turn ON the AC circuit breaker.
When the DC power generated by the solar array is adequate, the SOFAR
7K~10.5KTLM-G3 inverter will start automatically. Screen showing “normal”
indicates correct operation.
NOTE:
Choose the correct country code. (refer to section 6.3 of this manual)
Notice:
Different distribution network operators in different countries have different
requirements regarding grid connections of PV grid connected inverters. Therefore, it's
very important to make sure that you have selected the correct country code according to
requirements of local authority. Please consult qualified electrical engineer or personnel
from electrical safety authorities about this.
Detection methods of isolated islands:Reactive Power Disturbance.
Shenzhen SOFAR SOLAR Co., Ltd. is not responsible for any consequences
arising out of incorrect country code selection.
If the inverter indicates any fault, please refer to Section 7.1 of this manual ——
trouble shooting for help.
NOTE:The inverter can monitor the power grid in real time,The protection can
be realized when the power grid is abnormal, so that the inverter is separated
from the power grid.