3.2

MARK OUT HOLES

Consult SMP layout drawing for structure position on site.

See 

page 4 & 5

 for concrete foundation sizes.

NOTE:

This is a minimum guide only.

3.3

ESTABLISH DATUM LEVEL

i)

If a rubber tiled Impact Absorbing surface is to be laid, see separate instructions (base may incorporate up to
2% falls etc).

ii)

If equipment is to sit in loose fill or wet pour rubber surfaces allowances will need to be made for its
recommended thickness. Generally it is recommended that loose fill surfaces are installed to a depth of
300mm, however, with certain loose fill materials an alternative depth may be required. This will need to be
determined by allowing 100mm for the dispersal in addition to the thickness required for the particular Free
Fall Height. The foundation illustrated will allow for a thickness up to 300mm.

PRE-INSTALLATION INSPECTION 

Inspect all parts for damage (that may have occurred during transportation & storage). Finish Coatings, if found to be
damaged these should be made good before erection (Refer to maintenance instructions). Any damaged or missing
parts must be replaced.

4

INSTALLATION & ASSY PROCEDURES

i)

Refer to site layout for position and orientation of product, then, mark the outline of the position of the footings
with e.g. spray or chalk etc. Excavate the holes.

 (SEE PAGE 4/5)

.

ii)

Fit 1 off BTN 135 Bolt (item 5) to each Upright Post (item 1 - LTB8), secure using 1 off M16 Washer (item 14)
and M16 Nyloc Nut (item 15). Check counterbores and holes are clear, ensure BTN Bolts are located in the
shallow counterbore on inside of posts. Ensure slots of BTN Bolts are positioned vertically (rope must pivot
vertically only) and the pins are pulled into the grain of the timber when tightened. 

(STEP 1).

iii)

Assemble to 2.4m Plank (Item 1- PCH) 2 off Plate (item 4) using 8 off M10 X 50 Coach Screws (item 8) and
M10 Armour Rings (item 9). Fully tighten.

 (SEE STEP 2).

iv)

Place upright posts into designated excavations, rotate posts by 45° so all BTN Bolts are facing inward, as
shown. Brace in position and ensure all the posts are level, plumb and spaced to correct dimensions, this is
critical for the correct tension of the ropes.

 (SEE PAGES 4 & 5, STEP 3)

v)

Place 2 off 200mm Bollard Fixing Posts (item 10) into designated excavations, brace in position taking notice
of surface type and requirements. For Type 1/2 attach Bollard Fixing Posts (item 10) to Extension Posts (item
11) using 8 off M10 X 40 Hex. Bolt (item 12) and M10 Nut (item 13). 

(SEE PAGES 4 OR 5 & STEP 4A OR 4B).

vi)

Attach 1 off Rope (item 2) to Plate (item 4) which is connected to the Plank (item 1 - PCH), secure using 1 of
Pivot Bar (item 7) and M5 X 25 Grub Screw (item 6), utilise 2.5mm AF Allen Key ensuring grub screw goes
through Pivot Bar to full depth of tapped hole. Fully tighten. Repeat instruction for other 3 Ropes (item 2).

(STEP 5).

vii) Verify ropes fit - remove before concreting. 

(STEP 6).

viii) Fill the holes with concrete to the required level, taking into account any Impact Absorbing Surfacing

requirements. Ensure that the full volume of concrete is used. The top of the concrete should gradually (1:100)
slope down & outwards locally from the equipment upstand to the required level to form a watershed.

Concrete mix is recommended at:

1 part cement;

2 parts sand; 

4 parts aggregate; 

by volume with 20mm aggregate

(20 N/mm

2

 min compressive strength)

ix)

Keep installation off limits to the public until the concrete has completely cured. (Recommended initial curing
time is 48 hours). 

(STEP 6).

ISSUE B 25-04-2012

Содержание CAPE HORN EC202B

Страница 1: ...DOCUMENT MAY BE COPIED OR RE PRODUCED IN ANY FORM OR BY ANY MEANS WITH OUT THE EXPRESS WRITTEN PERMISSION OF SMP PLAYGROUNDS LTD E sales smp co uk W smp co uk T 44 0 845 260 1655 INSTALLATION INSTRUCTIONS CAPE HORN EC202S EC202B ...

Страница 2: ...CAPE HORN EC202 Page 2 ISSUE B 25 04 2012 ...

Страница 3: ...2 Section 1 Page 3 Section 1 EC202S 3 90 X 1 70 X 1 70 248 00 0 45 5 00 X 3 00 0 40m T 4h EC202B 261 00 0 49 x 2 T 6700 3250 0 40 m TYPE 1 2 3 101 144 1500R 1500R 1500R 1500R 1500R 1500R 1625 1625 ISSUE B 25 04 2012 ...

Страница 4: ...02 Section 1 Page 4 EC202B 3750 0 40 m 300 700 0 0 TYPE 1 2 101 144 1100 300 750 0 0 A 1 LTB8 3 450 X 450 775 1150 100 0 0 450 X 450 B A A A A B B 450 X 450 450 X 450 775 400 X 400 400 X 400 3450 ISSUE B 25 04 2012 ...

Страница 5: ...APE HORN EC202 Section 1 Page 5 EC202S 0 40 m 850 300 0 0 1 LTB8 3 TYPE 3 101 144 350 1150 1100 0 0 3750 A 775 450 X 450 A A A B B 450 X 450 450 X 450 775 400 X 400 400 X 400 3450 B A ISSUE B 25 04 2012 ...

Страница 6: ...S EC202B kg 1 781 018 1 51 00 X 4 10 90 X 1 2 780 504 4 0 50 3 RYBL200 2 7 5 4 780 559 2 1 62 5 780 593 4 0 40 6 780 594 8 0 003 7 780 595 8 0 02 8 786 925 8 0 03 9 10301002 8 0 014 LTB8 X 4 2800 2400 PCH X 1 910 CRS RTB4 200 MCH ISSUE B 25 04 2012 ...

Страница 7: ...00 11 305802 2 6 0 12 10231040 8 0 05 13 10261000 8 0 01 14 10381600 4 0 007 15 10321600 4 0 031 16 786 904 4 0 03 17 782 000 1 0 05 18 10051025 4 0 03 19 RYADHBK 1 20 10120400 1 420 Aro Seal 1132 Polyurethane Sealant http www alansonsuk com downloads asp ISSUE B 25 04 2012 ...

Страница 8: ...CAPE HORN EC202 Section 1 Page 8 STEP 1 1 LTB8 14 15 5 X 4 1 LTB8 ISSUE B 25 04 2012 ...

Страница 9: ...CAPE HORN EC202 Section 1 Page 9 STEP 2 1 PCH 9 4 1 PCH 8 8 9 4 ISSUE B 25 04 2012 ...

Страница 10: ...CAPE HORN EC202 Section 1 Page 10 STEP 3 1 LTB8 1 LTB8 0 0 3750 CRS 45 4 5 1550 CRS 45 45 45 1100 1700 ISSUE B 25 04 2012 ...

Страница 11: ...CAPE HORN EC202 Section 1 Page 11 STEP 4A EC202B 3450 CRS 12 13 X 2 11 0 0 TYPE 1 2 4 0 0 11 300 100 10 X 2 10 10 775 TYP 10 1550 CRS REF 4750 CRS REF 10 10 A A A A ISSUE B 25 04 2012 ...

Страница 12: ...CAPE HORN EC202 Section 1 Page 12 STEP 4B EC202S TYPE 3 5 775 TYP 4750 CRS REF 0 0 0 0 10 X 2 10 10 10 10 1550 CRS REF 3450 CRS A A A A ISSUE B 25 04 2012 ...

Страница 13: ...CAPE HORN EC202 Section 1 Page 13 STEP 5 X 4 6 7 2 4 1 PCH 1 PCH ISSUE B 25 04 2012 ...

Страница 14: ...CAPE HORN EC202 Section 1 Page 14 STEP 7 X 2 1 LTB8 4 5 STEP 6 1 LTB8 2 6 7 5 X 2 2 5 14 7 6 X 2 15 5 15 14 ISSUE B 25 04 2012 ...

Страница 15: ...CAPE HORN EC202 Section 1 Page 15 3 3 10 Aro Seal 1132 Polyurethane Sealant Black http www alansonsuk com downloads asp STEP 8 STEP 9 X 4 16 19 10 ISSUE B 25 04 2012 ...

Страница 16: ...CAPE HORN EC202 Section 1 Page 16 1 LTB STEP 11 STEP 10 500 17 18 1 LTB8 0 0 ISSUE B 25 04 2012 ...

Страница 17: ...02 Appendix A Page 17 Appendix A 144 TYPE 3 SYNTHETIC 144 TYPE 1 2 LOOSEFILL 1010 3270 1010 1010 1010 1010 6720 1010 1635 1010 1010 1635 1010 3270 1010 1010 1010 1010 6720 1010 1010 1635 1010 1635 ISSUE B 25 04 2012 ...

Страница 18: ...CAPE HORN EC202 Appendix A Page 18 144 TYPE 5 GRASSMATT FR 3750 1875 1775 1500 144 TYPE 5 GRASSMATT FR WEAR AREA 6000 2000 1000 1275 TYP 1500 TYP 1000 TYP 7000 ISSUE B 25 04 2012 ...

Страница 19: ...orbing Surface tested to EN1177 BS7188 beneath this play equipment Refer to manufacturers instructions for details of installation The surface should have a Critical Fall Height greater than the Maximum Free Fall Height of the equipment Constructional Space is the approximate working area required to lay out and assemble the equipment For the safe operation of this equipment it must be installed o...

Страница 20: ...ope must pivot vertically only and the pins are pulled into the grain of the timber when tightened STEP 1 iii Assemble to 2 4m Plank Item 1 PCH 2 off Plate item 4 using 8 off M10 X 50 Coach Screws item 8 and M10 Armour Rings item 9 Fully tighten SEE STEP 2 iv Place upright posts into designated excavations rotate posts by 45 so all BTN Bolts are facing inward as shown Brace in position and ensure ...

Страница 21: ...st pivot vertically only and pulled into the grain of the timber when tightened Allow the ropes to take the weight of the plank STEP 7 xiii Fit 2 off 200mm Bollards item 3 to Fixing Posts item 10 Apply adhesive item 19 to Fixing Post item 10 and slide Bollards item 3 onto posts until fully home Refer to instructions provided with adhesive STEP 8 xiv Fit 4 off Black PLastic Caps item 16 to cover fi...

Страница 22: ...CAPE HORN EC202 Appendix A Page 22 ISSUE B 25 04 2012 ...

Отзывы: