ASSEMBLE BACK PANEL 

SELECT: 

 

5 x 1.850m Wall Sheets 

1 x 2.520 m Top Plate (Red) 

1 x 2.520 m Bottom Plate (Green) 

60 x 30mm Galv Clouts 

8 x Rivets 

STEP 1: 

 

 

Lay out 1 x Top Plate and 1 x Bottom Plate on a 
flat surface as shown (corner cutouts to face in-
wards).  

STEP 2: 

 

 

Place 5 x 1.850 m wall sheets on top of timber 
Plates with bottom of sheets flush with each oth-
er.  

 

 

Rivet the sheets together on overlaps as shown

.

 

STEP 3: 

 

 

Nail the wall sheets to the Top Plate at each end making sure 
that the top of the sheets are flush with the top of the Top 
Plate and that the sides of the wall sheets overhang the Top 
Plate by 

15mm

 as shown. 

 

 

Check that the Top Plate is straight then nail wall sheets to 
the Top Plate, using two clouts per pan.  

STEP 4: 

 

 

Nail the wall sheets to the Bottom Plate at each end,  

     ensuring that each side of the wall sheets overhangs the                           

Bottom Plate by 

15mm

 and that the distance between  

     the Top and Bottom Plates is correct. (As shown) 
 

 

Check that the Bottom Plate is straight then nail   

     wall sheets to the Bottom Plate, using two clouts per pan

.

 

Std Shed —

 

Bottom Plate will protrude below wall sheet by 

approximately 10mm.  
 
Raised base plate shed —

 

Wall sheet will protrude below 

the Bottom Plate by 20mm

TOP PLATE 

BOTTOM PLATE 

BOTTOM PLATE 

1811mm 

1811mm 

TOP PLATE 

TOP PLATE 

15mm 

15mm 

1811mm 

1811mm 

BOTTOM PLATE 

15mm 

15mm 

TOP PLATE 

IMPORTANT—IF YOU CHOOSE TO RAISE YOUR TIMBER 

BASE PLATE –READ THE FOLLOWING; 

 

For sheds with Raised Base Plate option only (see page 5), deduct 

30mm from measurement shown between Top and Bottom Plates on 
all wall panels, so cladding protrudes 20mm below bottom plate

Содержание SS2525

Страница 1: ...ASSEMBLY INSTRUCTIONS SS2525 BASE SIZE 2 520m x 2 520m...

Страница 2: ......

Страница 3: ...or cladding used in Smart Store Sheds Wash all surfaces annually using a hose and soft nylon brush Within 2 km of coast wash every 3 months as above After a storm wash the cladding and the gutters as...

Страница 4: ...m Measurement along centre of sheet 2 Barge 1 350 m 4 Roof 1 350 m 10 Ridge Flashing 1 550m 2 Door 3 4 Sheet 1 810 m 2 Padbolt Support 0 140 m 1 TIMBER Spouting 2 550 m 2 Bottom Plates H4 Green Front...

Страница 5: ...te Front Bottom Plate Side Back Wall Sheets Front Wall Sheets Door Jambs Front Wall Sheet Door Side Flashing Hinge Door Brace Door Top Bottom Channel Ridge Beam Jack Stud Ridge Flashings x 2 5 ASSEMBL...

Страница 6: ...coming through from underneath During construction you may raise the bottom timber plate to allow the wall cladding to protrude 20mm below the bottom plate This will stop water flowing between the bot...

Страница 7: ...Rivet sheets together STEP 2 Position door side flash ings and assemble door as shown Drill and rivet as per dia gram ensuring rivets penetrate into door sheet STEP 4 Rivet door brace flashings onto b...

Страница 8: ...n STEP 3 Nail wall sheets to the Top Plate at each end making sure that the top corners of the sheets are flush with the top of the Top Plate and that the sides of the wall sheet overhang the Top Plat...

Страница 9: ...te using two clouts per pan STEP 4 Nail the wall sheets to the Bottom Plate at each end ensuring that each side of the wall sheets overhangs the Bottom Plate by 15mm and that the distance between the...

Страница 10: ...Ensure the door closes properly then fit remaining rivets STEP 3 Place 3 x Wall Sheets on timber plates and rivet the sheets together as shown Ensure that the top of the sheet is flush with the top o...

Страница 11: ...g someone to support the panels while they are screwed together Before fixing ensure that the Side Panel overlaps the Back Panel Using 4 x 40mm screws 2 per join screw the Top and Bottom Plates togeth...

Страница 12: ...heck that the shed is sitting level and square and that the diagonal Top Plate measurements are the same fig 1 JACK STUD TOP PLATE RIDGE BEAM fig 2 fig 3 15mm JACK STUD RIDGE BEAM TOP PLATE ROOF SHEET...

Страница 13: ...PLATE STEP 3 Position 1 x roof sheet slotted end facing back so that the top of the sheet is at the centre of the Ridge Beam and the side of the sheet over hangs the end of the Ridge Beam and the Top...

Страница 14: ...ckets evenly around the shed and fix to the Bottom Plate and the concrete slab A 10mm masonry drill bit is required OPTIONAL SENTRY FLOOR Position the Floor Joists centrally between the side Base Plat...

Страница 15: ......

Страница 16: ...s less than 200g m2 as published by Branz Warranty certificate being returned to manufacturer within 21 days of purchase together with proof of purchase This warranty does not cover the following Fast...

Отзывы: