background image

 

 

FOUNDATION 

SMART STORE WOODEN FLOOR  

 

 

The optional Smart Store kitset wooden floor is precut and de-
signed to be fitted into the shed after the shed is assembled. 

  

 

Assemble shed as per  instructions and fit floor last. 

          (see page 13 for details).  

CONCRETE SLAB FOR RAISED BASE PLATE SHED 

 

To build a raised concrete slab for your shed to sit on, we recom-

mend the following: 

 

 

The raised slab size should be 15mm smaller than the base 
size of the shed and at least 30mm above ground line. 

 

 

The slab should be 80mm thick in the middle and 100mm 
thick around the edges. 

 

 

The slab should be laid on a solid or compacted base. 

 

 

Plastic sheeting under slab will prevent moisture coming 
through from underneath

.

 

 

 

During construction, you may raise the  bottom timber 
plate to allow the wall cladding to protrude 20mm below 
the bottom plate. This will stop water flowing between 
the bottom plate and the concrete floor.  

          

See note on page 7.

 

80mm 

100mm 

7.5mm

 

20mm

 

Concrete Floor

 

Base Plate

 

Wall Cladding

 

RAISED BASE PLATE OPTION 

(For sheds placed on a raised concrete floor) 

No doubt by now you will have decided what sort of base you are putting down.  

Please read the section that applies to your situation. 

If you choose to pour a concrete base you will need to decide whether you wish to raise the base plate of your shed. 

This allows the cladding to protrude below the surface of the concrete  and ensures a  water tight pad.  

See concrete pad specifications below 

By choosing this option you will need to make the pad to the specification below. 

Содержание SS2020

Страница 1: ...ASSEMBLY INSTRUCTIONS SS2020 BASE SIZE 2 020m x 2 020m...

Страница 2: ......

Страница 3: ...r cladding used in Smart Store Sheds Wash all surfaces annually using a hose and soft nylon brush Within 2 km of coast wash every 3 months as above After a storm wash the cladding and the gutters as s...

Страница 4: ...255 m 2 Roof 2 200 m 4 Ridge Flashing 2 050 m 1 Door 3 4 Sheet 1 810 m 2 Barge 1 100 m 4 TIMBER Padbolt Support 0 140 m 1 Bottom Plates H4 Green Front Back 2 020 m 2 Spouting 2 050 m 2 Bottom Plates...

Страница 5: ...e Back Wall Sheets Front Wall Sheet Door Jambs Front Wall Sheet Door Side Flashing Hinge Door Brace Door Top Bottom Channel Ridge Beam Jack Stud Ridge Flashing 5 ASSEMBLE FRONT PANEL 6 ASSEMBLE WALLS...

Страница 6: ...coming through from underneath During construction you may raise the bottom timber plate to allow the wall cladding to protrude 20mm below the bottom plate This will stop water flowing between the bot...

Страница 7: ...Rivet sheets together STEP 2 Position door side flash ings and assemble door as shown Drill and rivet as per dia gram ensuring rivets penetrate into door sheet STEP 4 Rivet door brace flashings onto b...

Страница 8: ...s to the Top Plate at each end making sure that the top corners of the sheets are flush with the top of the Top Plate and that the sides of the wall sheet overhang the Top Plate by approx 15mm as show...

Страница 9: ...e using two clouts per pan STEP 4 Nail the wall sheets to the Bottom Plate at each end ensuring that each side of the wall sheets overhangs the Bottom Plate by 15mm and that the distance between the T...

Страница 10: ...the Door Jamb Flashing Ensure the door closes properly then fit remaining rivets STEP 3 Place 2 x Wall Sheets on timber Ensure that the top of the sheets are flush with the top of the Top Plate and t...

Страница 11: ...2 per join screw the Top and Bottom Plates together in the corners STEP 2 Repeat Step 1 with the second Side Panel ensuring that the Side Panel overlaps the Back Wall Panel STEP 3 Stand up the Front...

Страница 12: ...secure the Jack Studs to the underside of the Ridge Beam one at each end fig 1 Turn the Ridge Beam Jack Stud assembly over and place it on the timber Top Plate in a central position Secure with 2 x 75...

Страница 13: ...eet then using 1 x 40mm Weatherseal nail fix Roof Sheet through the pan into the Top Plate Repeat at the front ROOF ASSEMBLY CONT 12 STEP 4 Centralise the Roof at the right hand end with the Ridge Bea...

Страница 14: ...e Bottom Plate and the concrete slab A 10mm masonry drill bit is required OPTIONAL SENTRY FLOOR Position the Floor Joists centrally between the side Base Plates and skew nail each end with two 75mm na...

Страница 15: ......

Страница 16: ...s less than 200g m2 as published by Branz Warranty certificate being returned to manufacturer within 21 days of purchase together with proof of purchase This warranty does not cover the following Fast...

Отзывы: