STEP 5:

 

 

• 

Place barge flashings on roof at end of shed 
ensuring the diagonal trimmed end is facing 
out. (See diagram on pg 5)

 

 

• 

Rivet the Barge Flashings to the roof and the 
side wall, using four rivets on top of barge and 
four into the side (

fig.3

).

 

STEP 4:

 

 

 

• 

Position the second Roof Sheet, and rivet to first roof sheet as 

shown.

 

 

• 

Fasten off as per Step 2.

 

 

• 

Rivet and nail/screw off the remaining Roof Sheets, ensuring 

the ribs line up with the front Roof Sheets and the back Wall 

Sheets.

 

STEP 3:

 

 

• 

Position 1 x roof sheet  so that the top of the sheet is at the 
centre of the Ridge Beam and the side of the sheet over hangs 
the end of the Ridge Beam and the Top Plate by 15mm.

 

 

• 

Ensure the Ridge Beam and the Top Plate are straight.

 

 

• 

Nail /screw 4 x corners of the Roof Sheet as shown, ensuring 
the ribs on the Roof Sheet line up with the front Roof Sheet 
and the back Wall Sheet. Fasten off the first sheet.

 

STEP 6:

 

 

• 

Rivet the 2 Ridge Caps together using 4 
rivets, so total flashing is 3.050m long. Rivet 
the Ridge Flashing to the centre of the roof 
using 10 x rivets as shown (

fig.2

).

 

 

= Clout

 

= Screw

 

SIDE

 

WALL

 

BACK WALL

 

TOP PLATE

 

BOTTOM PLATE

 

SIDE

 

WALL

 

RIDGE 

FRONT 

WALL

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

SIDE

 

WALL

 

fig.1

 

FRONT WALL

 

BACK WALL

 

SIDE

 

TOP PLATE

 

BOTTOM PLATE

 

SIDE

 

WALL

 

FRONT WALL

 

BACK WALL

 

SIDE

 

TOP PLATE

 

BOTTOM PLATE

 

fig.3

 

X 4

 

X 4

 

Barge

 

Spouting

 

fig.4

 

STEP 7:

 

 

• 

Place spouting in position and rivet to Barge Flashings 
at each end and rivet to roof sheets (1 rivet per 1 
sheet) 

(fig.4).

 

fig.2

 

Содержание SM3030

Страница 1: ...ASSEMBLY INSTRUCTIONS SM3030 BASE SIZE 3 020m x 3 020m...

Страница 2: ...cess needs to be adhered to to qualify for the steel warranty of your Duratuf Smart store shed Wash all surfaces annually using a hose and soft nylon brush Within 2 km of coast wash every 3 months as...

Страница 3: ...1 850m 4 Door Jamb 1 890m 2 Door Brace 1 160m 2 Door Brace 0 915m 2 Double Door Weatherstrip 1 850m 1 Barge 1 602m 4 Ridge Cap 1 800m 2 Door Top Bottom 0 945m 2 Door Top Bottom 0 495m 2 Jack Studs 45...

Страница 4: ...TION QTY DIAGRAM Front Back Bottom Plates H4 Green 3 020 m 2 Front Back Top Plate H1 Red 3 020 m 2 Side Wall Bottom Plates H4 Green 3 020 m 2 Side Wall Top Plates H1 Red 3 020 m 2 Ridge Beam 140 x 45...

Страница 5: ...EMBLE DOOR QUICK OVERVIEW Door Sheets Padbolt Support Top Plate Back Side Wall Sheets Roof Sheets Top Plate Side Top Plate Front Bottom Plate Front Bottom Plate Side Back Wall Sheets Front Wall Sheets...

Страница 6: ...ng through from underneath During construction you may raise the bottom timber plate to allow the wall cladding to protrude 20mm below the bottom plate This will stop water flowing between the bottom...

Страница 7: ...flat surface making sure narrow pans are on the outside Rivet sheets together ensuring ends are flush with each other STEP 2 Position door side flashings and 0 945m top and bottom flashings and assem...

Страница 8: ...the Top Plate 2 clouts per pan see fig 1 Standard Shed Bottom Plate will protrude be low wall sheet by approximately 10mm Raised base plate shed Wall sheet will protrude below the Bottom Plate by 20mm...

Страница 9: ...sing two clouts per pan STEP 4 Nail the wall sheets to the Bottom Plate at each end ensuring that each side of the wall sheets overhangs the Bottom Plate by 15mm and that the distance between the Top...

Страница 10: ...eets are flush with the top of the Top Plate and that the sides of the wall sheets overhang the Top Plate by 15mm as shown Nail wall sheets to Top Plate two clouts per pan Nail the wall sheets to the...

Страница 11: ...2 per join screw the Top and Bottom Plates together in the corners STEP 2 Repeat Step 1 with the second Side Panel ensuring that the Side Panel overlaps the Back Wall Panel STEP 3 Stand up the Front...

Страница 12: ...RIDGE BEAM fig 2 fig 3 15mm JACK STUD RIDGE BEAM TOP PLATE ROOF SHEET STEP 2 Position the first Roof Sheet so that the top of the sheet is at the centre of the Ridge Beam and the side of the sheet ove...

Страница 13: ...s the end of the Ridge Beam and the Top Plate by 15mm Ensure the Ridge Beam and the Top Plate are straight Nail screw 4 x corners of the Roof Sheet as shown ensuring the ribs on the Roof Sheet line up...

Страница 14: ...ORROSION AND COULD THEREFORE VOID THE WARRANTY FIT PADBOLT Rivet Padbolt to door and keeper onto Door Jamb as shown 14 YOUR DURATUF SMART STORE SHED IS NOW COMPLETE RELAX FRONT BASE PLATE BACK BASE PL...

Страница 15: ......

Страница 16: ...s less than 200g m2 as published by Branz Warranty certificate being returned to manufacturer within 21 days of purchase together with proof of purchase This warranty does not cover the following Fast...

Отзывы: