4  CAN bus functional test

SMA Solar Technology AG

Service Manual for Installers

SBSx.x-10-CAN-SG-en-10

10

6. Remove the cover of the inverter and remove the test cable from battery interfaces 

BAT1

 and 

BAT2

.

7.

Check battery interfaces BAT3 and BAT4:

• Now use the test cable to connect 

BAT3

 and 

BAT4

 on the battery interface module.

• Close the cover of the inverter.

• Switch on the AC fuse.

• Log in to the interface of the inverter as 

Installer

.

• In the 

Device parameters

 menu, at 

Edit parameters

,

select 

Battery

. Under 

Operation > Can test mode

, enter

34

 as value and confirm with 

Save all

.

☑ If the CAN interfaces 

BAT3

 and 

BAT4

 are fault free, the

Events

 menu shows 

success rate: 100

.

Because the communication cable to the battery has been
removed for the functional test, the list of events might show
various error messages relating to battery communication,
although the CAN interface is working perfectly.

☑ The CAN interface check is complete. No further settings are required.

8. Disconnect the inverter from the voltage sources again (see inverter manual).

9. Remove the cover of the inverter and remove the test cable from battery interfaces 

BAT3

 and 

BAT4

.

10. Insert the terminal blocks with the communication cable to the

battery or backup box into the respective 

BATx

 input again.

BAT1

BAT2

BAT3

11. Use the AC circuit breaker to switch on the inverter.

12. Switch on the battery or the load-break switch of the battery (see documentation of the battery manufacturer).

13. Log in to the interface of the inverter as 

Installer

.

14. At the top right of the user interface, click on the 

 symbol.

15. In the drop-down menu, select the option 

Starting the Installation Assistant

 and follow the instructions of the

installation assistant.

☑ After the installation assistant has been completed successfully, the configured system is available again and is

ready for operation.

If the communication error persists, the inverter can be excluded as cause. The origin of the communication error is in a
different area of the installation.

Detecting a defective CAN input

• If, when CAN interfaces 

BAT1/BAT2

 or 

BAT3/BAT4

 are being tested and the value mentioned above has been

entered and confirmed, the 

Events

 menu shows 

"success rate: 0"

 instead of 100, one of the CAN inputs are

defective.

In the event of a defective CAN input, a service request has to be submitted and the battery interface
module has to be replaced.

Содержание SUNNY BOY STORAGE 3.7-10

Страница 1: ...SBSx x 10 CAN SG en 10 Version 1 0 ENGLISH Service Manual for Installers Functional test of the CAN interface SUNNY BOY STORAGE 3 7 10 5 0 10 6 0 10...

Страница 2: ...ble of Contents 1 Information on this Document 3 1 1 Validity 3 1 2 Target Group 3 1 3 Content and Structure of this Document 3 2 IMPORTANT SAFETY INSTRUCTIONS 4 3 Background Information 7 4 CAN bus f...

Страница 3: ...iring and using electrical devices batteries and installations Training in the installation and commissioning of electrical devices and installations Knowledge of all applicable laws standards and dir...

Страница 4: ...s in death or lethal injuries due to electric shock Ensure that all devices in the same network and the battery are integrated into the existing surge protection When laying the network cables or othe...

Страница 5: ...truction of the measuring device due to overvoltage Overvoltage can damage a measuring device and result in voltage being present in the enclosure of the measuring device Touching the live enclosure o...

Страница 6: ...oisture can penetrate the product and damage it Only open the product if the ambient temperature is not below 0 C If a layer of ice has formed on the enclosure seal when temperatures are below freezin...

Страница 7: ...able used to connect the CAN interfaces on the battery interface module in the inverter with the battery is not suitable see requirements in the manual of the inverter The inverter has not been ground...

Страница 8: ...inverter Two 6 pole terminal blocks Assignment of the terminal block Terminal block Position Assignment A B C D E F A Not assigned B Not assigned C GND D CAN L E CAN H F Not assigned Procedure On both...

Страница 9: ...nverter You can find the current firmware versions at https www sma de service downloads html Please read the accompanying Readme files before updating In the Device parameters menu at Edit parameters...

Страница 10: ...test cable from battery interfaces BAT3 and BAT4 10 Insert the terminal blocks with the communication cable to the battery or backup box into the respective BATx input again B A T 1 B A T 2 B A T 3 11...

Страница 11: ...5 Contact SMA Solar Technology AG Service Manual for Installers 11 SBSx x 10 CAN SG en 10 5 Contact https go sma de service...

Страница 12: ...www SMA Solar com...

Отзывы: